(Ward will be hosting the call as Bjorn is
traveling.)
Agenda:
- RC0 status from each project.
According to our schedule Platform, CDT, DTP, EMF, GEF, and VE have
completed their RC0 and BIRT, GMF, TPTP, and WTP should complete their RC0
this Friday. What is the status of these RC0s? Will we have a final Callisto
RC0 on Friday?
- Update Site. Will we have an RC0
update site on Friday? Are all the projects sending their update site
information to David? How are we handling the "RC0 is in the midst of being
released one step at a time while M5 is the milestone on the update site" -
are we using our staging update site?
- RC1. According to our schedule,
RC1 is also this Friday. Thus the RC0 and RC1 are, for everyone except the
Platform, the same event. Does everyone agree?
- RC2 status from each project.
According to our schedule, RC2 is in two and a half weeks. What ramp
down policies are the projects applying for RC2? How many days delay is each
project using for RC2? When will the Platform go to RC2? After that, when will
CDT, DTP, ..., etc have their RC2s? And when will BIRT, GMF, TPTP, and WTP
have their RC2s? Will this all happen by 28-April?
- Ramp Down Policy from each project.
What ramp down policy is each project applying? How many sign-offs
are required to release a change? What notifications are sent for each change
and to whom? Etc.
- Bug Contest. The bug contest has
very few (I think two legitimate) entrants. Does anybody have an idea why?
Bugs but no good ones? No bugs being entered?
We're coming into the end game now which means that
we need to ramp up communication and coordination. I think the goal for this
call should be to come away with a concrete plan from each project for the end
games and the coordination and the tightening build schedule and to make sure
that we have the update site working.
Thanks,
Bjorn
|