Re: [mpwg] Gap Analysis: Questions on Cost Estimation

Christophe,

Thank you for providing feedback to our report. Please find my comments below:
 
For 2011, the effort estimation is 24 PY. Does this mean that the participating companies would have to invest 24/<NbOfInvolvedCompanies> full time person during one year,
No, this wouldn't be feasible. Even if we had enough funding it would not be realistic to assume that we could put a team of 24 people across different companies together and make sure that they collaborate in a coordinated and efficient way. There needs to be a significantly smaller group and some sort of ramp up to get this successfully started.
or are you considering that a part of the work will be managed by the current development teams?
It is sure that the current development teams will continue to do things in 2011 even if no funding at all would come from the Modeling Platform Working Group. But there wouldn't be any guarantee as to which extend these works would cover the Modeling Platform requirements and when the results would be shipped.
In the second case, could it be possible to know (more or less, I know it is Open Source), the extra effort the participating companies would have to provide?
The gap analysis, which is the first part of the planning study, indicates only the efforts that are required to be made regardless of who will finally take charge them and who will provide the necessary funding. In the second part of the planning study we will work on a roadmap in which we are going to address these aspects, i.e., which implementer companies would participate, which is the realistic number of resources that each of them could contribute, which of the prio 1 work packages could be realized, and which deliverables and milestones could be scheduled.

But again, for the sake of providing a project plan that is realistic and executable, we cannot base it on results which may or may not be achieved in the open source space but is not really under our control.
Showing these figures to my management will not have the expected result. Saying that we will have to provide/pay for 6 persons for this project will never be accepted.
We are aware of this problem and therefore will think of a way of providing a useful result without requiring an investment as high as what the gap analysis currently indicates. The roadmap which we will ship by end of October will propose such a way.
 
Regarding the estimation itself, am I wrong saying that your estimation and proposal is strongly coupled with a repository provider?
What do you mean by repository provider? Is it a model repository like CDO?
In the very first versions of the requirements, it was wished to be “Loosely coupled to different repository providers” (line 49 of the Excel sheet of the 24/02/2010 sent by Ian).
Assuming that the answer to my question above it yes, I'd say that this requirement correspond to requirement 1.3 + E-Config-1 "Support for different model repository types" in A1 "Version Management" in the gap analysis spraedsheets. The detailed capabilities of this requirement explain what kind of repository types are to be addressed.
Is it planned in the current architecture to be able to easily change some part of the platform?
Clearly yes. This includes the capacity of swichting between different model repository types as well as supporting model repositories, files-based SCMs or both in parallel. However, from other feedback which we have got so far we have concluded that this is not going to be a no 1 priority. The focus of the first iteration therefore would be on supporting one model repository type, namely CDO, and to some extend also file-based SCM systems.
Thanks and regards,
 
Christophe
 
PS: I read Ian’s mail about prioritization, but this will just stretch the project over time.
What we can learn from the gap analysis already now is that the gap between exisiting Eclipse modeling technology and the Modeling Platform requirements is pretty big (and maybe significantly bigger than many of us had hoped). It therefore will not be realistic to assume that ALL capabilities that are currently have a prio 1 can be realized within 2011. It will be unavoidable to make choices, i.e., reprioritize the prio 1 capabilities, and yes, decide which of them can be left to a later iteration.

I all the same believe that it will be possible to identify a subset of the prio 1 capabilities that fits into the 2011 schedule and will make up something useful. We then would be able to work on that subset in a coordinated way and address success-critical aspects like consistent integration to a complete platform, system testing based on real world use cases, etc. in an appropriate manners. So, compared to trying to do more that what is achievable and ending up with nothing, we will eventually have more by doing less.

Kind regards,

Stephan 
_______________________________________________ mpwg mailing list mpwg@xxxxxxxxxxx https://dev.eclipse.org/mailman/listinfo/mpwg

--

Dr. Stephan EBERLE

----------------------------------------------------------------

Product Development Manager

 

6 avenue de Verdun

92250 La Garenne Colombes, France

 

Phone : +33 (0)1.73.54.00.30

Fax : +33 (0)1.73.54.00.32

Mobile : +33 (0)6.64.18.39.10

 

E-mail : stephan.eberle@xxxxxxxxxxx

www : http://www.geensys.com

----------------------------------------------------------------


Back to the top