Update for BIRT project
1. Have
you finished your RC1 bits?
Yes. It is the same BIRT RC0 bits, finished testing on platformRC1.
2. If
not, when do you expect to finish them?
3. If
you're waiting for another project, which one(s)? will test with
RC1a on Monday. And package BIRT downloads with RC1a.
4. Have
you placed those bits in your update site?
yes.
5. Have
you updated the features.xml file in the Callisto CVS directory? yes
6. Are
you ready for RC1 to be declared? yes.
Wenfeng
-----Original
Message-----
From:
eclipse.org-planning-council-bounces@xxxxxxxxxxx
[mailto:eclipse.org-planning-council-bounces@xxxxxxxxxxx] On Behalf Of Bjorn Freeman-Benson
Sent: Thursday, April
20, 2006 2:04 PM
To: eclipse.org-planning-council;
Cross project issues
Subject:
[eclipse.org-planning-council] RC1 Status? Please reply to the listwith your
status and bits
Callisto People,
I'm confused about our status and I think probably other people are too so
could everyone send an email to the list with your RC1 status information:
7. Have
you finished your RC1 bits?
8. If
not, when do you expect to finish them?
9. If
you're waiting for another project, which one(s)?
10. Have
you placed those bits in your update site?
11. Have
you updated the features.xml file in the Callisto CVS directory?
12. Are
you ready for RC1 to be declared?
I know that some of you have already sent your status
to the list, but if you could do so again, that would be much
appreciated. Thank you.
I am out of town for the next week, so David Williams graciously agreed to
gather the information and potentially bug you if you haven't sent an email to
the list, etc.
Thanks,
Bjorn