Re: [wtp-dev] WTP Release 1.5 Shutdown Process


Arthur,

The doc says that the final release build will be June 14th and only extremely serious bugs will be allowed after that.  RC5 runs until June 20th, does that mean there are different rules after June 14th?

Also, I was under the impression the Eclipse Platform does not follow these same procedures with all this overhead for getting bugs into a build.  I thought they used a system allowing one PMC member to act as the PMC as a whole to vote on such matters and that one vote is sufficient.  Is there a reason WTP is not acting in this manner?

Thanks,

John Lanuti
Software Engineer, IBM Rational
jlanuti@xxxxxxxxxx
t/l 441-7861

"I know this lady way down in my country.
She is so pretty that my eyes throw disguises at me.
Now we will sit and we'll wonder about our future,
But now I'm thinking that today sounds fine to me."  - Of A Revolution



Arthur Ryman <ryman@xxxxxxxxxx>
Sent by: wtp-dev-bounces@xxxxxxxxxxx

06/06/2006 12:34 AM

Please respond to
"General discussion of project-wide or architectural issues." <wtp-dev@xxxxxxxxxxx>

To
wtp-dev@xxxxxxxxxxx, wtp-pmc@xxxxxxxxxxx
cc
Subject
[wtp-dev] WTP Release 1.5 Shutdown Process






For your viewing pleasure, I have created a Wiki page [1] that describes the shutdown process. Please review and comment. Thx.


[1] http://wiki.eclipse.org/index.php/WTP_Release_1.5_Shutdown_Process


Arthur Ryman,
IBM Software Group, Rational Division

blog: http://ryman.eclipsedevelopersjournal.com/
phone: +1-905-413-3077, TL 969-3077
assistant: +1-905-413-2411, TL 969-2411
fax: +1-905-413-4920, TL 969-4920
mobile: +1-416-939-5063, text: 4169395063@xxxxxxx
_______________________________________________
wtp-dev mailing list
wtp-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/wtp-dev


Back to the top