[eclipselink-dev] 1.0M1 Exit Criteria & Schedule
|
EclipseLink
Component Leads and Developers,
I have been working
on an initial roadmap (http://wiki.eclipse.org/EclipseLink/RoadMap)
and want to start working on a more concrete plan for an initial milestone as we
move towards a 1.0 release. I would like to get a concrete set of exit criteria
for 1.0M1 and then we can work backwards on what needs to be done and pull
together a schedule.
My rough thinking on
what we may want to include
- Deliver the functionality included in the initial
contribution. No new features planned beyond what has been
done.
- Add descriptions
on RoadMap as well as document the use
cases that users should expect to work
- Complete initial
component organization of source and tests
- Automated build
process - nightly?
- Testing
- Automated nightly
testing on MySQL or Derby?
- LRG defined and
working for OracleDB and MySQL/Derby that developers can use to validate
check-ins
- Server testing
available for manual execution?
- JPA CTS run by
Oracle
- Packaging
- Only JAR and
src.ZIP (No OSGi bundle for this milestone)
- Ensure proper
about.html file(s) created and populated
- Distributable
incubation.zip with allowed dependencies and document for additional
required dependencies
- Wiki
Content
- Organize content
to clearly address users versus those who wish to develop or integrate
EclipseLink
- Users:
How to
get started with EclipseLink JPA, EclipseLink MOXy, and EclipseLink
SDO
- Developers:
Explain components, how to build, how to test
Please provide your
feedback on this list any any other items you feel we need to
address. If there are functional bugs
then we should get them filed in the Eclipse bugzilla and add them to the exit
criteria.
This milestone
is targeted at early adopters and is not an official Eclipse release as we are
still an incubation project. The priority is getting through a milestone and
working out the processes. I want to plan milestone builds at a relatively fixed
so consumers can gain confidence and rely on our scheduling.
Please provide you
feedback by the end of the week (COB Friday September 14th) and we can schedule
a meeting for next week to discuss open issues and nail down our exit
criteria.
Doug