Hi David, all
since I can't promise to make the call (can't reach the asterisk server from home right now and might have to pick up my daughter around the time of the call) I'd leave my 2 cents:
Since SR2 is important but probably not mission critical for adaptors I think that we can afford a delay without bad consequences. Delivering something which could harm users data is a lot worse.
>From our perspective having a full respin seems the best way. It would require some work from everyone (especially from you and Markus) but I don't consider the 2 weeks delay that bad (There is always a first time for everything, even a late Eclipse release ;-) ).
Doing a "composite" looks like the next best solution with a lot less work.
All other options listed in the Wiki will also force a delayed release and don't really fix the problem or look risky.
Achim
Quoting David M Williams <david_williams@xxxxxxxxxx>:
PC Members,
I assume most of you have seen the notes on cross-project, epp, and elsewhere about last minute problems with SR2.
Seems serious enough we should make a decision as a group, and understand impact of delay and amount of delay, to members and Eclipse community.
Sorry for the late notice, but hope most of you can make that call.
I'll prepare an "agenda page" within an hour and try to capture what I think high level alternatives are, but will need at least your feed back on those alternatives, if not better alternatives.
Thanks,
--------------------------------------------------------
BREDEX GmbH
Mauernstr. 33
38100 Braunschweig
Tel.: +49-531-24330-0
Fax: +49-531-24330-99
http: www.bredex.de
Geschäftsführer: Achim Lörke, Ulrich Obst, Andreas Vogel
Amtsgericht Braunschweig HRB 2450
|