From: eclipse.org-planning-council-bounces@xxxxxxxxxxx
[mailto:eclipse.org-planning-council-bounces@xxxxxxxxxxx] On Behalf Of Bjorn Freeman-Benson
Sent: Wednesday, May 23, 2007 1:12
AM
To: eclipse.org-planning-council
Subject: Re:
[eclipse.org-planning-council] Agenda for 5/23 Europa call
There's nothing wrong with having your bits done
early. Yes, I put a little extra slack at the end in case we needed to re-spin
builds for whatever reason. If we need to have an RC5 that week to pick up your
last bits, I'm ok with that. Of course if your bits cause breakage, then we'll
just drop them and retreat, but with your high quality C-powered bits, how
could there ever be a problem? :-)
One question I do have. When we did the CDT plan a few months
ago, we had targeted June 22 as our final build date with bi-weekly RC builds
starting at the end of April leading up to that, thinking that was plenty of
time to make the Europa end date of June 29. Looking at the Europa schedule, I
see now that we are planning the last RC for June 20. I’m not sure what
all the extra time between the final build and Europa release on June 29 is
supposed to be for. The mirrors only take a couple of days to update. Or is
this built-in slack?