RE: [eclipse-pmc] Helios end game plan

With the recent changes the freeze plan sounds good to me.

>Do you have data at hand what had caused the delays?
It's not just for the RCs. Over the years we learned that building later on
Thursday often resulted in slipping into Saturday. Note that for the normal
milestones we even declare THU 0100 as final build.

Dani

|------------>
| From:      |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |"Oberhuber, Martin" <Martin.Oberhuber@xxxxxxxxxxxxx>                                                                                              |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
|------------>
| To:        |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |<eclipse-pmc@xxxxxxxxxxx>, "Thomas Watson" <tjwatson@xxxxxxxxxx>                                                                                  |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
|------------>
| Date:      |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |15.03.2010 16:17                                                                                                                                  |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
|------------>
| Subject:   |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |RE: [eclipse-pmc] Helios end game plan                                                                                                            |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|





> I think this change is necessary because last year we proved incapable of
producing a good build in less than 24 hours.

This concerns me.

Do you have data at hand what had caused the delays?

Martin

From: eclipse-pmc-bounces@xxxxxxxxxxx [
mailto:eclipse-pmc-bounces@xxxxxxxxxxx] On Behalf Of John Arthorne
Sent: Monday, March 15, 2010 3:57 PM
To: eclipse-pmc@xxxxxxxxxxx; Thomas Watson
Subject: [eclipse-pmc] Helios end game plan


Fellow PMC members,

According to the Helios simultaneous release requirements, we must make our
end game plan available by Helios M6, which is this coming Friday the 19th.
I have written an initial draft of this end game plan here:

http://www.eclipse.org/eclipse/development/plans/freeze_plan_3.6.php

Apart from the usual one day shift in dates, I have made two changes from
last year:

1) Removed one day from the RC2 test pass, to make it a single day test
pass. The feedback during the Galileo retrospective was that the extra
testing at this point was too late in the cycle. Instead teams would like
some extra testing earlier in the end game. I have *not* added this extra
testing, since I thought we should discuss with the whole team during this
week's planning call. The two choices are to have a test pass immediately
after M7 for two days, or to start the M7 shutdown a couple of days earlier
to allow for an extended M7 test pass. I can update the the freeze plan
once we decide on that.

2) Moved the RC builds from Thursday 8pm to Thursday 8am (EDT). This is
unfortunate because it cuts down on the time available for the fix pass.
Hopefully teams that *do* make a good contribution the first time can spend
all of Thursday and Friday doing either testing or fixing for the next
week's RC. I think this change is necessary because last year we proved
incapable of producing a good build in less than 24 hours. From the
archives, this is when we shipped each RC last year:

3.5 RC1 Saturday 9am
3.5 RC2 Sunday 7pm
3.5 RC3 Friday 5pm
3.5 RC4 Sunday 9pm

Hopefully making the build 12 hours earlier will help us hit closer to the
target this time around. When we slip our milestone/RC dates it causes
great disruption to the +1 projects that need to have their builds
completed on the following Monday.

Comments and criticism welcome on any aspect of the freeze plan, either my
two proposed changes or any other aspect of the plan that has not changed
from last year. We can discuss on this list, and/or during Wednesday's call
this week. Also let me know if there are any national holidays in countries
where we have committers that I missed. It's useful to have these marked in
the freeze plan for reference.

John_______________________________________________