Hi folks,
Following up on my last email from the council meetings, here
are some tentative dates for milestones on Europa – the next Eclipse train
release.
Doug
From: cross-project-issues-dev-bounces@xxxxxxxxxxx
[mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] On Behalf Of John
Arthorne
Sent: Thursday, July 20, 2006 11:20 AM
To: Cross project issues
Subject: Re: [cross-project-issues-dev] Europa milestones needed
If it helps,
the eclipse platform project is tentatively targetting the following dates for
the first milestones, following the usual six week rhythm:
Thursday Aug. 10, 2006 - Milestone 1 (3.3 M1) -
stable build
Friday Sep. 22, 2006 - Milestone 2 (3.3 M2) -
stable build
Friday Nov. 3, 2006 - Milestone 3 (3.3 M3) - stable
build
Friday Dec. 15, 2006 - Milestone 4 (3.3 M4) - stable build
These dates will be confirmed when the first draft of the 3.3
plan is released, either at the end of this week or early next week.
John
I know we
discussed the general flavor of the Europa milestones at the Chicago planning
council, but as September approaches the projects will need definitive dates
for at least the first of these, and ultimately the calendar for the rest of
the year. Are we ready to set these dates?