[cross-project-issues-dev] Indigo Simultaneous Release Train : which milestone for UI freeze ?

Hi,

there is something which is not obvious to me about UI freeze deadline.
The page (http://eclipse.org/indigo/planning/EclipseSimultaneousRelease.php) describes the API freeze as required for M6 but it does not talk about UI freeze.

I have seen on some Project plans M7 marked as "feature freeze" or "UI freeze".
Could someone tell if there are some requirement on "UI freeze" for M6 ?

Thanks,
Fabien Giquel