Re: [cross-project-issues-dev] DSDP-TM requests delaying our M6 dropby 4 days

Title: New Page 1
It's been a general project management philosophy at Eclipse never to slip dates: always slip features, never slip dates.
As far as I know, we don't currently have any consumers who require
strict train date. But we do have consumers who much rather download
a Milestone for their personal use and adoption, rather than an I-build
or an M6 and later M6b ...
So Martin is saying that (1) "dates don't matter to his consumers" and (2) "his consumers want to use M-builds rather than I-builds".  The obvious question then is "why not have his consumers use M7/RC0?"  If dates don't matter, and that's the next M-build, then it seems like problem solved... ??

- Bjorn
--
[end of message]