What’s our agreed to policy
regarding Callisto dates and slips of early dependencies. E.g., Callisto
RC1 states the three categories of deliveries as absolute dates. But, how
can the +1 and +2 categories deliver on the absolute date if the earlier
dependency is not available on time.
In this specific case, what is the
expected impact to the Callisto RC1 schedule related to Eclipse Platform delivering
RC1a as their Callisto RC1 contribution (later than Apr 14)?
RC1 (14-Apr .. 21-Apr)
Starting with RC1, each project will apply its own
ramp-down rules.
·
14-Apr - Platform
·
19-Apr - CDT, DTP, EMF, GEF, VE
·
21-Apr - BIRT, GMF, TPTP, WTP
From:
cross-project-issues-dev-bounces@xxxxxxxxxxx
[mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] On Behalf Of Kim Moir
Sent: Thursday, April 20, 2006
7:30 AM
To: Cross
project issues
Subject:
[cross-project-issues-dev] platform RC1a will be contributed tocallisto RC1
Just a FYI, the platform ran another build toward RC1a
for the following issue identified by the WTP team.
https://bugs.eclipse.org/bugs/show_bug.cgi?id=135107
http://dev.eclipse.org/mhonarc/lists/platform-releng-dev/msg06480.html
Therefore,
we will not be be contributing platform RC1 to callisto, but platform RC1a
Kim