Good question. Give that it’s a
major release and the major theme is API change (just kidding J)… Actually it’s
up to the committers as a group. When will everyone be comfortable with an API
freeze? Code freeze, i.e. the point where we only fix bugs, will likely happen
in sync with the Platform which will likely be sometime during April next year.
We had a nice two month ramp down this year that worked very well. With all the
churn coming in 4.0, we may need a bit longer, something like mid-Apr to end-June.
From:
cdt-dev-bounces@xxxxxxxxxxx [mailto:cdt-dev-bounces@xxxxxxxxxxx] On Behalf Of Sennikovsky, Mikhail
Sent: Thursday, July 20, 2006
11:58 AM
To: CDT
General developers list.
Subject: RE: [cdt-dev] FW:
[cross-project-issues-dev] Europa milestones needed
Hi Doug,
>Hey
gang, here are the target milestones currently under consideration by the
Platform. Europa, the next simultaneous release which will include CDT 4.0,
usually follows these by a couple of weeks. End of August might be a great time
for CDT 4.0 M1. Something to think about.
Given
that M1 is in the end of August and M4 is in the end of December-beginning of
January 2007(following to the platform plan below), when are the API freeze and
Code freeze should happen?
I’m
asking because I’d like to know what time slot we will have for the 4.0
development.
Thanks,
Mikhail
From:
cdt-dev-bounces@xxxxxxxxxxx [mailto:cdt-dev-bounces@xxxxxxxxxxx] On Behalf Of Doug Schaefer
Sent: Thursday, July 20, 2006 7:23
PM
To: CDT
General developers list.
Subject: [cdt-dev] FW:
[cross-project-issues-dev] Europa milestones needed
Hey
gang, here are the target milestones currently under consideration by the
Platform. Europa, the next simultaneous release which will include CDT 4.0,
usually follows these by a couple of weeks. End of August might be a great time
for CDT 4.0 M1. Something to think about.
From:
cross-project-issues-dev-bounces@xxxxxxxxxxx
[mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] On Behalf Of John Arthorne
Sent: Thursday, July 20, 2006
11:20 AM
To: Cross
project issues
Subject: Re:
[cross-project-issues-dev] Europa milestones needed
If it helps, the eclipse platform project is tentatively targetting the
following dates for the first milestones, following the usual six week rhythm:
Thursday Aug. 10, 2006 - Milestone 1 (3.3 M1) -
stable build
Friday Sep. 22, 2006 - Milestone 2 (3.3 M2) -
stable build
Friday Nov. 3, 2006 - Milestone 3 (3.3 M3) - stable
build
Friday Dec. 15, 2006 - Milestone 4 (3.3 M4) - stable build
These dates will be confirmed when the first draft of the
3.3 plan is released, either at the end of this week or early next week.
John
"Tim Wagner"
<twagner@xxxxxxx>
Sent
by: cross-project-issues-dev-bounces@xxxxxxxxxxx
18/07/2006
12:34 PM
Please respond
to
Cross project issues
<cross-project-issues-dev@xxxxxxxxxxx>
|
|
To
|
"Cross project issues"
<cross-project-issues-dev@xxxxxxxxxxx>
|
cc
|
"WTP PMC communications (including coordination,
announcements, and Group discussions)" <wtp-pmc@xxxxxxxxxxx>
|
Subject
|
[cross-project-issues-dev] Europa milestones needed
|
|
I know we discussed the general flavor of the Europa milestones at the Chicago planning council,
but as September approaches the projects will need definitive dates for at
least the first of these, and ultimately the calendar for the rest of the year.
Are we ready to set these dates?