the target milestones currently under consideration by the Platform. Europa,
the next simultaneous release which will include CDT 4.0, usually follows these
by a couple of weeks. End of August might be a great time for CDT 4.0 M1.
Something to think about.
Given that M1 is in
the end of August and M4 is in the end of December-beginning of January 2007(following
to the platform plan below), when are the API freeze and Code freeze should
happen?
I’m asking
because I’d like to know what time slot we will have for the 4.0
development.
Thanks,
Mikhail
From:
cdt-dev-bounces@xxxxxxxxxxx [mailto:cdt-dev-bounces@xxxxxxxxxxx] On Behalf Of Doug Schaefer
Sent: Thursday, July 20, 2006 7:23
PM
To: CDT
General developers list.
Subject: [cdt-dev] FW:
[cross-project-issues-dev] Europa milestones needed
Hey gang, here are the
target milestones currently under consideration by the Platform. Europa, the
next simultaneous release which will include CDT 4.0, usually follows these by
a couple of weeks. End of August might be a great time for CDT 4.0 M1.
Something to think about.
From:
cross-project-issues-dev-bounces@xxxxxxxxxxx [mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx]
On Behalf Of John Arthorne
Sent: Thursday, July 20, 2006
11:20 AM
To: Cross
project issues
Subject: Re:
[cross-project-issues-dev] Europa milestones needed
If it helps, the eclipse platform project is tentatively
targetting the following dates for the first milestones, following the usual
six week rhythm:
Thursday Aug. 10, 2006 - Milestone 1 (3.3 M1) -
stable build
Friday Sep. 22, 2006 - Milestone 2 (3.3 M2) -
stable build
Friday Nov. 3, 2006 - Milestone 3 (3.3 M3) - stable
build
Friday Dec. 15, 2006 - Milestone 4 (3.3 M4) - stable build
These dates will be confirmed
when the first draft of the 3.3 plan is released, either at the end of this
week or early next week.
John
"Tim Wagner"
<twagner@xxxxxxx>
Sent
by: cross-project-issues-dev-bounces@xxxxxxxxxxx
18/07/2006
12:34 PM
Please respond
to
Cross project issues
<cross-project-issues-dev@xxxxxxxxxxx>
|
|
To
|
"Cross project issues"
<cross-project-issues-dev@xxxxxxxxxxx>
|
cc
|
"WTP PMC communications (including coordination,
announcements, and Group discussions)" <wtp-pmc@xxxxxxxxxxx>
|
Subject
|
[cross-project-issues-dev] Europa milestones needed
|
|
I know we discussed the general flavor of the Europa
milestones at the Chicago
planning council, but as September approaches the projects will need definitive
dates for at least the first of these, and ultimately the calendar for the rest
of the year. Are we ready to set these dates?
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev