Re: [wtp-pmc] 3.1 Milestone schedule..


Hi Raghu,

Yes, the one published on the weekly agenda is correct and should be followed.

As David said we've decided to stick with the Thursday smoketest and Friday build declaration cycle, while the Galileo +2 dates may be on the Wednesday after.
I can add in the official Galileo dates at the bottom if that helps.


Regards,

Helen Zhang PMPĀ®
Rational Architecture Management Project Management Office
Eclipse Webtools Platform (WTP)

IBM Toronto Software Lab | 8200 Warden Ave. | Markham | L6G 1C7
Email: hjzhang@xxxxxxxxxx | Phone: 905-413-3443 | T/L: 969-3443



David M Williams/Raleigh/IBM@IBMUS

10/09/2008 03:09 PM

To
"WTP PMC communications \(including coordination, announcements, and Group discussions\)" <wtp-pmc@xxxxxxxxxxx>
cc
Helen Zhang/Toronto/IBM@IBMCA
Subject
Re: [wtp-pmc] 3.1 Milestone schedule..Link




Not sure which is correct, but Helen can you check and reply?
Please make sure both are aligned with the Galileo dates we discussed?

Helen and I went over some of these dates and the ones in the earlier milestones, we set our own WTP delivery for Friday,
even if the Galileo +2 date was the following Wednesday. In all the cases we looked at, it seemed easier (and achievable) to do early
than to mess up the Friday rhythm. We should note those cases with a footnote, so we don't lose track of where we tweak.

Thanks,




From: Raghunathan Srinivasan <raghunathan.srinivasan@xxxxxxxxxx>
To: "WTP PMC communications (including coordination, announcements, and Group        discussions)" <wtp-pmc@xxxxxxxxxxx>
Date: 10/09/2008 02:47 PM
Subject: [wtp-pmc] 3.1 Milestone schedule..





Hi,
 
The dates for each of the 3.1 milestones in the Project plan are different from those published on the WTP status page. Are these the official dates for WTP?
 
http://wiki.eclipse.org/WTP_2008-10-02#Schedule
 
3.0.1 Early Maintenance Release Aug 15
M1 -> Aug 22 (extra week added so not to overlap maintenance release)
3.0.2 Coordinated Maintenance Release Sep 24
M2 -> Sept 26 (extra week added so not to overlap maintenance release) (updated)
M3 -> Nov 7 (short milestone, since "making up" for added week above)
M4 -> Dec 19
M5 -> Feb 6
3.0.3 Coordinated Maintenance Release Feb 25
(EclipseCon March 23-27)
M6 -> Mar 20 Feature Complete, API Freeze, UI Freeze, NLS, Accessibility
M7 -> May 8 Performance tuning, documentation, bug fixing
RC1 -> May 22 Serious bugs only, focus on stability.
RC2 -> May 29 WTP will likely not participate in an RC2, based on feedback from last year that RC2 came too soon, needed more fixing, less testing
RC3 -> Jun 5 Very serious bugs only.
RC4 -> Jun 12 Very very serious bugs only.
RC5 -> Jun 19 Hopefully no changes from RC4. Prepare web pages, update sites, etc.
GA -> Jun 24
-Raghu