Re: [technology-pmc] [ORMF] updated project plan
|
+1
Wayne
Joel Rosi-Schwartz wrote:
Hi.
After due consideration, Barbara and I have decided to modify the
project plan slightly. Essentially we have slotted in a new iteration
after I1 and reduced the (excessively long) duration of the RC
iterations at the end of our plan. The end date of release is the same.
The motivation for this change is the fact that, having decided to
create a survey[1] for requirements standards that involves external
requirements experts, we feel that we won't be able to have the
results of the survey ready until the end of I1 and therefore we need
an extra iteration to be able to validate our requirements model
against the results of the survey.
Thanks and regards,
Joel
[1] Survey of requirements management standards [Call for
participation] (see Bugzilla issue)
------------------------------------------------------------------------