On 18/08/14 11:10 PM, David M Williams
wrote:
http://wiki.eclipse.org/Mars/Simultaneous_Release_Plan#Schedule
I have modified our Mars schedule
slightly
since our last meeting. At that meeting it seemed clear we could
not "compress"
M6 enough to finish before EclipseCon, so we made M6 a week
longer to 7
weeks duration, so it would not end while EclipseCon was ending.
But, that
still left the +0 teams ending when EclipseCon ended, which is
less that
desirable, since that would mean their final "stabilization
week"
would completely overlap with EclipseCon.
After the meeting, I realized
another
undesirable feature was still left over from last year's
compression: we
allowed only 6 weeks for M5, which traditionally we allowed 7
weeks for,
since it spanned "end of year" holidays.
So, to solve both problems, I
added
a week to M5 (making it 7 weeks long). Slipped M6 a week to the
right so
that the +0 day would be a week after EclipseCon was over (but
still 7
weeks in duration), and thus resulting in there being only 6
weeks for
M7.
It seems the best solution to me,
given
when EclipseCon is scheduled, but would appreciate members of
the planning
council proofreading and reviewing it soon, so at our next
meeting any
issues will have already been discussed, adjustments made if
needed, and
we can call it final.
Thanks,
_______________________________________________
eclipse.org-planning-council mailing list
eclipse.org-planning-council@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/eclipse.org-planning-council
IMPORTANT: Membership in this list is generated by processes internal to the Eclipse Foundation. To be permanently removed from this list, you must contact emo@xxxxxxxxxxx to request removal.
--
Wayne Beaton
@waynebeaton
The Eclipse Foundation

|