Scott, if the 2.0.0 is what you're releasing as your part of Ganymede, 
you don't need a separate review. But if there's something in it that 
isn't part of Ganymede, then you will need a separate release. The 
Ganymede review call is June 4, and I think the actual release date is 
June 28. We aren't scheduling any non-Ganymede releases until June 25 
because the IP team doesn't have time for non-Ganymede reviews right 
now. I hope this makes sense. Thanks.
Anne Jacko
emo@xxxxxxxxxxx
On May 14, 2008, at 3:22 PM, Scott Lewis wrote:
Hi Anne,
Is the 25th early enough so that we can release 2.0.0 as part of 
Ganymede?  I can't remember the Ganymede release date but isn't it 
around the same time?
And RE: the IP log...don't they have to review our IP log as part of 
the Ganymede release (since we're in Ganymede?).
Scott
Anne Jacko wrote:
Hi Scott,
How about June 25? But first you'll need to verify with Janet that 
her team will be able to approve your IP Log in time. They have been 
swamped with Ganymede work so we need to firm statement from them 
that they can do the necessary approval by June 18 for the June 25 
review. Thanks.
Anne Jacko
emo@xxxxxxxxxxx
On May 14, 2008, at 1:46 PM, Scott Lewis wrote:
Hi Anne,
ECF would like to request the scheduling of an ECF2.0.0 release 
review.  We are part of the Ganymede release and will be 
participating in the Ganymed Simultaneous Review on June 4, so 
would like to have the ECF 2.0.0 release review sometime *after* 
that review.
Thanks,
Scott