From: cross-project-issues-dev-bounces@xxxxxxxxxxx [mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx]
On Behalf Of David M Williams
Sent: Thursday, May 01, 2014 11:49 AM
To: cross-project-issues-dev@xxxxxxxxxxx
Subject: [cross-project-issues-dev] Reminder that M7 is just days away ....
As we in the Platform are preparing for our final +0 contribution for M7, just wanted to remind everyone that M7 +3 is near, and ...
A. Three projects are still disabled due to change in ICU version conflicting with BIRTs version ... would have been good to have a "warmup" build correcting that, so at least dependent projects can be re-enabled
to make sure no surprises.
Bug 432464 - Temporary disabled BIRT, MAT, and Stardust for Luna warm up builds
B. Appears many still missing "required legal files":
http://build.eclipse.org/simrel/luna/reporeports/reports/layoutCheck.txt
And while looking at that list ... I couldn't help but wonderer what is the "mycorp" project?
Such as, in the list is com.mycorp.examples.timeservice...
Granted, it is an example, and granted, I do not know the exact "Eclipse rules", but I would think best if even examples used their "eclipse namespace"?
C. Appears some progress in warming up with new SUA
http://build.eclipse.org/simrel/luna/reporeports/reports/licenseConsistency.html
License Consistency Summary
-
Features with conforming (2014) license: 184
-
Features with old (2011) license: 857
-
Features with old (2010) license: 8
-
Features with different (or no) license: 13
-
Features with no license attribute: 0
-
Features with extra licenses: 0
D. I am curious why signing is so hard?
http://build.eclipse.org/simrel/luna/reporeports/reports/verifydiroutput/unsigned.txt
I'm just crack'n the whip ... appreciate everyone's efforts and contributions.
Much thanks,