Hi,
 
The dates for each of the 3.1 milestones in the Project plan
are different from those published on the WTP status page. Are these the
official dates for WTP?
 
http://wiki.eclipse.org/WTP_2008-10-02#Schedule
 
3.0.1 Early Maintenance Release Aug 15 
M1 -> Aug 22 (extra week added so not to overlap
maintenance release) 
3.0.2 Coordinated Maintenance Release Sep 24 
M2 -> Sept 26 (extra week added so not to overlap
maintenance release) (updated) 
M3 -> Nov 7 (short milestone, since "making
up" for added week above) 
M4 -> Dec 19 
M5 -> Feb 6 
3.0.3 Coordinated Maintenance Release Feb 25 
(EclipseCon March 23-27) 
M6 -> Mar 20 Feature Complete, API Freeze, UI
Freeze, NLS, Accessibility 
M7 -> May 8 Performance tuning, documentation, bug
fixing 
RC1 -> May 22 Serious bugs only, focus on
stability. 
RC2 -> May 29 WTP will likely not participate in an
RC2, based on feedback from last year that RC2 came too soon, needed more
fixing, less testing 
RC3 -> Jun 5 Very serious bugs only. 
RC4 -> Jun 12 Very very serious bugs only. 
RC5 -> Jun 19 Hopefully no changes from RC4.
Prepare web pages, update sites, etc. 
GA -> Jun 24
-Raghu