Updated from previous version with
comments from last week’s PMC call.   General Post M5 Process: 
 All (provisional) API
     changes require project lead approval All changes require associated
     Bugzilla entry PMC will review defect
     convergence on a weekly basis (daily as needed during final RC candidate
     production)    Week of July 3: 
 RC1 produced Any defect can be addressed
     Component lead must code review
     and approve all fixes (enter into Bugzilla record and checkin notes)
        Week of July 10: 
 RC2 produced P1/2 only can be addressed
     All checkins must have Bugzilla
     entry Component lead must code review
     and approve    Week of July 17: 
 RC3 produced, if needed
     P1 only can be addressed
     Project lead (or designate)
     must approve; component lead must code review (enter both names into
     Bugzilla record and checkin notes) All changes
     communicated to wtp-dev mailing list   Week of July 24: 
 Intent is to verify only;
     RC’s produced as needed, and will likely move ship date out
     P1 only can be addressed in
     additional RC's PMC approval required
     for any changes (plus protocol from previous week) All changes
     communicated to wtp-dev mailing list and newsgroup   Final review: 
 No P1’s admitted (i.e.,
     no ship-killer defects known) All automated tests passing on
     final RC All shipping platforms have
     been tested All component leads sign off on
     individual components PMC votes to release
        --------------------------------------------------------------------------------
Join CEO Alfred Chuang and CTO Mark Carges on June 15 for a unique online 
event, giving you the first look at a new category of enterprise software 
built specifically for Service-Oriented Architecture (SOA).
Register Now.  It's Free!
http://www.bea.com/events/june15
 |