Greetings PMC.
    We have a situtation.
    The XWT project team has apparently stopped participating in the
      simultaneous release process. According to the EDP, the XWT
      project must engage in a release review before the version 1.2
      bits can be released. If they do not engage in this review, then
      we have to remove them from the simultaneous release.
      Unfortunately, at least two other projects in the simultaneous
      release depend on XWT, so removing it will be at least a little
      bit painful. I'm assuming that these dependent projects have done
      sufficient testing of their features that depend on XWT.
    
    Theoretically, if we remove them from the release, the projects
      that use XWT can revert to an earlier version. That's one option
      to consider. Perhaps those projects may be able to extract
      themselves from XWT.
    
    Another option is for us to declare the project dysfunctional,
      retire the current project lead and team, and then push it through
      the process ourselves. Then, following the release, we first look
      for another team to take over the project or take steps to
      terminate and archive the project.
    I've sent a note to the dev-list and personal note to the project
      lead in a last-ditch effort to get a response. If we don't hear
      back before Monday, we'll have to make a decision.
    
      Wayne