Any
advice on the API requirement the requested reports?
Doug
Not really. That field is meant reference the executive summary that you
should have provided to the EMO (in your mini-deck) along with your complete
release review slides. If you can sum that up in one or two sentences then I
suggest you just put that summary in the field on the portal. Otherwise you
can create a small html page on your project site to refer to. I don't think
we will be able to have a single executive summary for all of RT. Instead I
think each project lead under RT should come up with their own
summary.
Tom
Markus
Alexander Kuppe ---06/02/2010 12:03:57 PM---On 06/02/2010 06:32 PM, Thomas
Watson wrote:
 From: |
 Markus Alexander Kuppe
<rt-pmc_eclipse.org@xxxxxxxxxxx> |
 To: |
 rt-pmc@xxxxxxxxxxx |
 Date: |
 06/02/2010 12:03 PM |
 Subject: |
 Re: [rt-pmc] Tracking compliance for
the Helios release |
On 06/02/2010 06:32 PM, Thomas Watson wrote:
> We are at
the end of the development cycle for the Helios release. The
> planning
council is tracking our progress more closely now. Please
> update your
tracking data soon (see
> http://eclipse.org/helios/planning/SimultaneousReleaseGrid.php?projectid=rt
>
for the RT status)
Hi,
the portal says something about "PMC's
Executive Summary". I assume a
link to [0] or [1] will do? Otherwise from
where do we get this summary?
Markus
[0] http://dev.eclipse.org/mhonarc/lists/rt-pmc/pdfEJmKntygzf.pdf
[1]
http://dev.eclipse.org/mhonarc/lists/rt-pmc/msg01759.html
_______________________________________________
rt-pmc
mailing list
rt-pmc@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/rt-pmc