Skip to main content

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [List Home]
[openMobility] FW: [openMobility-sc] 2022 Program Plan and Budgeting Process Cycle Announcement
  • From: <Robert.Hilbrich@xxxxxx>
  • Date: Mon, 4 Oct 2021 06:18:47 +0000
  • Accept-language: de-DE, en-US
  • Delivered-to: openMobility@xxxxxxxxxxx
  • Ironport-data: A9a23:WXZu3KwCvVFxxmmrlXV6t+ekxCrEfRIJ4+MujC+fZmUNrF6WrkUBy WofC2mGOK3fYGXzc9wiPISx8RkEu8KBn94xHARkrVhgHilAwSbn6XV1DatS0we6dJCroJdPt p1GAjX4wUNdokb0/n9BCJC4xZVH/fzOFueU5NLsYHgrHFY8EHt50HqPpsZg6mJWqYnha++yk Y6qyyHvEAfNN+lcaz98Bwqr8XuDjdyq0N8qlgVWicNj4Dcyo0Io4Kc3fsldGZdZrr58RYZWT 86bpF2wE/iwEx0FUrtJmZ6jGqEGryK70aFjRRO6VoD76iWuqBDe3Y4HGcQzcXxaqwzUlvBdz cRtnp6tWTgAa/ikdOQ1C3G0EglSGYFr1pHiAF2H65C+/2aAcn3w2fwoAEUse4EVkgp1KTgWs 6VIdHZUNUDF3b7eLLGTE4GAguwZK8PmJp9ZmnBkxyvYBvYOTZTZBanHjTNd9Gpg2JERQqmED yYfQRpxZT//eTBSAWlNIo0+guWJ3kfiVzIN/Tp5ooJyuQA/1jdZ16DgNv/ScN2ORNlEtkuTo mPe5Gm/BQsVXOFz0hKJ9n6hiOHKnCbjAt4fBLb+9/h2mlTVymgJThEbPbemncSEZoeFc4o3A yQpFuAG9MDeKGTDogHBYiCF
  • Ironport-hdrordr: A9a23:iqD976p/0hNubXfd+ZCtC7IaV5oFeYIsimQD101hICG9Kvbo8/ xG785rsiMc6QxhIk3I9urhBEDtex7hHNtOkOws1NSZLXTbUQmTXeJfBOLZqlWKcREWtNQtt5 uIGJIQNDSENzlHZLHBjjVQfexN/DDNytHPuQ6X9QYVcehFUdAZ0+82YDzraXFLeA==
  • Ironport-phdr: A9a23:WK1MBxfj2QvkH23IEeLZcrIdlGM+dN7LVj580XLHo4xHfqnrxZn+J kuXvawr0AWRG9yKsrkd07OempujcFRI2YyGvnEGfc4EfD4+ouJSoTYdBtWYA1bwNv/gYn9yN s1DUFh44yPzahANS47xaFLIv3K98yMZFAnhOgppPOT1HZPZg9iq2+yo9JDffRlEiCCgbb52M Rm6ohjdutULjYB/Nqs/1xzFr2dSde9L321oP1WTnxj95se04pFu9jlbtuwi+cBdT6j0Zrw0Q rNEAjsoNWA1/9DrugLYTQST/HscU34ZnQRODgPY8Rz1RJbxsi/9tupgxCmXOND9QL4oVTi+6 apgVRjnhjoaNz4i6GHYlNB/jL5VrhKmohxw2Y/UYIeIP/Z6ca7QedYWSGxcVchTSiNBGJuxY YsRAeQcIeZWoYrzp1UMohu/GQajC/jiyjpUin/0x6A2z/gtHAPA0Qc9H9wOqnPUrNDtOaoVT e61y7LHwivZb/NKwzvz6onIchQ6rvGWXLJ/bcrRxFIyGAPBlFWcs5HqMC2M2+kLrmOU4PZuW /i1hG47twF+vCKvxsE0h4TImI8YxF/J+Tt3zosrJtC1S1N2b9CkHZZNqi2WK4V7T90iTWxqp io0xKAKtJy1cSQXxpkqyQDTZv6DfoSU7R/uUvuaLzl/hHJgYr2/hhCy/FCvyu37Ucm031JKo TRfntbQsXAN0hre4dWERPtl5kqtxCqD2xrO5uxHLk04j7fXJpAiz7IqiJYevlzPEjLqlEnsk aObdUop9vK15+npYbjqvIGQOo97hwz4L68ggNawAf4iPQgLR2Wb/OO826D98kDhW7VKi+E2k rHesJDHOcQXvq65DBFR0oYk8xuxATGo3toXk3cHLFxLfxGJgY/zNV3QL/32Avawjkq2nDdqw fDGIqfhDY/XInfelLfhZ6xx5FNCxwYrzNBf4YxbCq0ZLf7uRkP9rsHUAxw2PgCu3urqBtZw2 pkAVW+AGqOZNbndsV6M5uIhOemMY4oVtS7hJfgi/PHhk2U5mUMHcaer3JsXbGu3Hu5nI0qFY XrhmcoOEWMQvgYkUePllkWOUSRPaHaqQ6I8+jY7BZqhDYfbWI+thruP3CCgEZ1XYmBGC0yME HfzeoqaR/gMbCOSItd6kjMaT7ShTJUh1R79/DP9nu5gNufS3yoStJbiyMld6ubXlAkp+HpzF cvLgE+XSGQhylkPTTIswOZfoEh30FaI0YB0h+YeGdEFtKABaRszKZOJl78yMNv1QA+UIobhd Q==
  • Ironport-sdr: ORxAMcHsMrTP/cUJBop0ncKuKCyhhTzURmAVb5UFgq+wAzNkqYqVZGAAPtvFUQjQfH8Rt5D4xm Y5u0Xjrqaf8Q==
  • List-archive: <https://www.eclipse.org/mailman/private/openmobility/>
  • List-help: <mailto:openmobility-request@eclipse.org?subject=help>
  • List-subscribe: <https://www.eclipse.org/mailman/listinfo/openmobility>, <mailto:openmobility-request@eclipse.org?subject=subscribe>
  • List-unsubscribe: <https://www.eclipse.org/mailman/options/openmobility>, <mailto:openmobility-request@eclipse.org?subject=unsubscribe>
  • Thread-index: AQHXtsoU0xsdMPm+0ki5jRkG1RRwDKvCYY/g
  • Thread-topic: [openMobility-sc] 2022 Program Plan and Budgeting Process Cycle Announcement

FYI – we should talk about that tomorrow…

 

From: openMobility-sc <openmobility-sc-bounces@xxxxxxxxxxx> On Behalf Of Sharon Corbett
Sent: Friday, October 1, 2021 3:41 PM
To: openmobility-sc <openmobility-sc@xxxxxxxxxxx>
Subject: [openMobility-sc] 2022 Program Plan and Budgeting Process Cycle Announcement

 

Dear Steering Committee:

October has arrived which means Eclipse Foundation Working Groups must start the annual process of program plan creation and budget finalization for calendar year 2022.  

 

This process needs to commence no later than early October (next week) with a candidate Program Plan created and subsequently approved by the steering committees no later than November 5, 2021.  Please note Budget finalization must be in place no later than November 19th to align with the Foundation’s budget cycle.  Please see the following components, milestones and timeline:

Program Plan Development 

·  Solicit Input/Ideas from Working Group membership (Early October)

·  Draft Program Plan Created (Mid October)

·  Candidate Program Plan Approved by Steering Committee (Due November 5, 2021)

Budget Development 

·  Eclipse Foundation develops budget based on program plan priorities (Early November)

·  Final Budget reviewed and approved by Steering Committee (Due November 19, 2021)

Timeline

 

image.png

 

This timeline is necessary in order for Executive Director approval prior to inclusion in the Eclipse Foundation’s overall budget.

 

To provide assistance with this process, we have arranged the following resources:

 

·  2022 Program Plan and Budget Process (Refresher)

·  2022 Program Plan and Budget Process (Full Version)

·  2022 Sample Program Plan Slide Deck Template (Make a copy or reuse past templates)

 

This is also the time for steering committees to review 2021 program plans with a view of completing any remaining achievable objectives and to work with the Foundation team to do so. As a reminder, working groups are expected to apply the fees collected towards program priorities in the year they are received.

 

Additionally, in mid-to-late October the Eclipse Foundation team will provide steering committees with similar budget reporting to that provided following Q2.   For newer working groups, this could very well be the first such report.


Should you have any questions, please do not hesitate to contact your Program or Community Manager or reach out to me or Paul Buck directly.


Best Regards,


Sharon Corbett

Program Director, Working Group Operations

Eclipse Foundation

_______________________________________________
openMobility-sc mailing list
openMobility-sc@xxxxxxxxxxx
To unsubscribe from this list, visit https://accounts.eclipse.org

Back to the top