Henrik,
It's not a problem to delay the release, except perhaps for your
community, but if you communicate with them effectively I'm sure
they'd prefer a good quality stable release as opposed to a
premature release that immediately requires a maintenance release.
Regards,
Ed
On 06/05/2013 12:12 PM, Henrik wrote:
Hi PMC members and
Wayne,
our eTrice relase 0.3 was scheduled for April 30th. Everything
is approved and reviewed (see [1]).
Now it turned out that we are behind schedule already and due to
conference talks, customer projects and vacation we won't be
able to ship the 0.3 release before 14th of June.
To our knowledge there is nobody really waiting for the release.
So we would prefer to postpone the release than shipping a
poorly documented one (since documentation for the new features
is the major open working package).
Unfortunately the beginner's tutorials for the C target language
are so much outdated that they don't work at all anymore.
So we feel it wouldn't make sense to release in this state.
Does it pose a problem to move the release date by 6 weeks?
Thanks,
Henrik