Hi All,
Looking at the WBS for the various phases i.e. inception, elaboration,
construction etc, they all end with a “sequential” activity for assessing
and planning the next iteration. I think this is unnecessarily
restrictive. Most other activities are performed in parallel so why must
the assessment of the current iteration and planning for the next be
sequential?
As a suggestion couldn’t the planning tasks be made part of manage
iteration? And don’t we continually assess status? If there is a
sequential activity at the end of an iteration I’d rather think of it as
“publish next iteration plan” which could include a status assessment.
Regarding the stated purpose of the Assess Results task i.e. “Determine
success or failure of the iteration. Apply the lessons learned to modify
the project or improve the process.” I don’t have any problems with the
second sentence but I do with the first sentence, the “success or
failure”. I think if you are applying the process properly, it cannot be a
“failure”, a setback maybe but “success of failure” promotes the wrong
connotations for iterative development.
Regards Chris
Chris Doyle
Solution Specialist
Synergy Plus Pty Ltd