[eclipse.org-planning-council] Staging the next iteration


I don't know what the best solution is, but one problem I've spotted with this schedule is the
March 13th M6 date.

That does not give enough time for "the train" to have a milestone before EclipseCon (23rd)

Ideally, M6 +0 would be one week earlier (or two?) so that the whole train could have a milestone
right before EclipseCon. Especially since the closest other milestones, M5 Will be approximately
a full month before EclipseCon (approx. Feb 20th?)

If it is not possible to move "in" the March 13th date, we may want to come up with some radical plan
such as to have an M5-prime build be "the" EclipseCon build. (M5 prime would be on the Platform's M5,
but plus something beyond the standard M5 delta dates, so more can be included to "show off" at EclipseCon.

Or, maybe plain 'ol M5 is fine for the EclipseCon build, with the train's M6 to follow EclipseCon.

I raise this now, mostly just for other projects to think about as they develop their detailed plans ... that is,
not sure we need to solve it right now ... but should over next few months.

Thanks,







From: Philippe P Mulet <philippe_mulet@xxxxxxxxxx>
To: Cross project issues <cross-project-issues-dev@xxxxxxxxxxx>, eclipse.org-planning-council@xxxxxxxxxxx
Date: 07/16/2008 12:15 PM
Subject: [eclipse.org-planning-council] [cross-project-issues-dev] Staging        the next iteration (whatever it        is named)






Here it is again (take 3), with fix for a missing week in M7. Allocated one more week in M7 to compensate for EclipseCon distraction.


M1 - August 8, 2008 (6 weeks)
>>>  (3.4.1/Ganymede-SR1 +0 dates:  RC1-September 1, RC2-September 8, RC3-September 15)

M2 - September 19, 2008 (6 weeks) - PLANNING

M3 - October 31, 2008 (6 weeks) - DEV

M4 - December 12, 2008 (6 weeks) - DEV

M5 - January 30, 2009 (7 weeks) - MAJOR FEATURE WORK COMPLETED
>>>  (3.4.2/Ganymede-SR2 +0 dates:  RC1-February 2, RC2-February 9, RC3-February 16)

M6 - March 13, 2009 (6 weeks) - API FREEZE, FEATURE TUNING, I18N & ACCESSIBILITY

>>>  (EclipseCon March 23-27)
M7 - May 1st, 2009 (7 weeks) - PERFORMANCE & POLISH, BEST EFFORT ON DOC
RC1 (2 weeks) - May 15, 2009
RC2 (1 week) - May 22, 2009
RC3 (1 week) - May 29, 2009
RC4 (1 week) - June 5, 2009





__________________



Already found a typo in M1:



M1 - August 8, 2008

M2 - September 19, 2008

M3 - October 31, 2008

M4 - December 12, 2008

M5 - January 30, 2009 (one extra week to compensate for Christmas break)

M6 - March 13, 2009

(EclipseCon March 23-27)

M7 - April 24, 2009

RC1 - May 15, 2009

RC2 - May 22, 2009

RC3 - May 29, 2009

RC4 - June 5, 2009

Final - June 12, 2009





 

__________________


In parallel of the discussion for a good name for the next iteration, I would like to know what its staging might look like (at least for the +0 dates) ?

Here are my first suggestions in case none was made already:


M1 - August 10, 2008

M2 - September 19, 2008

M3 - October 31, 2008

M4 - December 12, 2008

M5 - January 30, 2009 (one extra week to compensate for Christmas break)

M6 - March 13, 2009

(EclipseCon March 23-27)

M7 - April 24, 2009

RC1 - May 15, 2009

RC2 - May 22, 2009

RC3 - May 29, 2009

RC4 - June 5, 2009

Final - June 12, 2009




Sauf indication contraire ci-dessus:/ Unless stated otherwise above:

Compagnie IBM France

Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 Courbevoie

RCS Nanterre 552 118 465

Forme Sociale : S.A.S.

Capital Social : 542.737.118 euros

SIREN/SIRET : 552 118 465 02430




Sauf indication contraire ci-dessus:/ Unless stated otherwise above:

Compagnie IBM France

Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 Courbevoie

RCS Nanterre 552 118 465

Forme Sociale : S.A.S.

Capital Social : 542.737.118 euros

SIREN/SIRET : 552 118 465 02430



_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev


Sauf indication contraire ci-dessus:/ Unless stated otherwise above:
Compagnie IBM France
Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 Courbevoie
RCS Nanterre 552 118 465
Forme Sociale : S.A.S.
Capital Social : 542.737.118 euros
SIREN/SIRET : 552 118 465 02430
_______________________________________________
eclipse.org-planning-council mailing list
eclipse.org-planning-council@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/eclipse.org-planning-council

IMPORTANT: Membership in this list is generated by processes internal to the Eclipse Foundation.  To be permanently removed from this list, you must contact emo@xxxxxxxxxxx to request removal.



Back to the top