Re: [e4-dev] Delay M3 by 1 week? response required
|
+1 from me. Without delaying, the milestone would not be very interesting and perhaps not worth the extra milestone effort we put in (like the N&N, testing etc).
Boris
Paul Webster ---01/04/2010 12:46:59 PM---With many people coming back off the Christmas break I've had a couple of requests to delay the M3 m
![]()
From: | ![]()
Paul Webster <pwebster@xxxxxxxxxxxxxxxxxxx> |
![]()
To: | ![]()
E4 Project developer mailing list <e4-dev@xxxxxxxxxxx> |
![]()
Date: | ![]()
01/04/2010 12:46 PM |
![]()
Subject: | ![]()
[e4-dev] Delay M3 by 1 week? response required |
![]()
Sent by: | ![]()
e4-dev-bounces@xxxxxxxxxxx |
With many people coming back off the Christmas break I've had a couple
of requests to delay the M3 milestone by 1 week, to allow the teams to
stabilize their M3 changes. I'm not against this.
Old: Jan 8th, 2010 [1]
New: Jan 15th, 2010
This will not effect the date of M4, Feb 19th.
So the question is: Do we delay M3 until next week? As usual, I need
3 +1s and no -1s from the committers. I'll make a decision by
Tuesday, Jan 5th at 12:00 EST.
Later,
PW
[1] http://wiki.eclipse.org/E4/Builds#Milestone_Builds
--
Paul Webster
Hi floor. Make me a sammich! - GIR