RE: [dsdp-mtj-dev] MTJ Plan Change Proposal
 | 
Title: MTJ Plan Change Proposal
I agree with the proposed changes. We need more time to 
finalize the apis before the freeze. It is far easier to delay and get the apis 
right the first time than to go back and fix them later.
 
Eric Hildum
Senior Product Manager, Mobile Developer 
Tools & SDK
Developer Platforms and 
Services
Ecosystem and Market 
Development
Motorola
Direct: +1-408-541-6809
 
809 11th Avenue
Sunnyvale, CA 94089
USA
 
Hi MTJ,
Since we still have 
a 
lot of inputs on the APIs we would like 
to proposal a change on out initial 
MTJ Plan. Based on our 
original 1.0 plan we wants to have our API freeze on MTJ M6 (Mar. 
16th.). But, since there are no other Eclipse 
projects that will consume our API and we need more time to review / propose changes on the API, we want to change those dates.
The proposed plan 
is:
-       Design new APIs until 
M6 (Mar. 16th.) 
-       Commit initial API 
code as soon as it is ready 
-       Iteration on the design and code until 
RC1 (May 18th.) 
-       
After RC1 changes need to be approved by MTJ committers and public discussed on 
the list 
That will give the 
community around two months to review and propose changes on 
the MTJ API. Does anyone have 
anything against this change?
If we can do this change 
on the plan, there are still two 
new E.P. that we plan to submit:
-       sdkInstall E.P.: 
proposed by danail 
-       pre/post build  E.P. 
we will work to send 
initial proposals of them on the 
wiki
Comments on the proposed 
plan are welcome.