[cross-project-issues-dev] 2021-12 Schedule changed

Hi,

Pay attention that the release cycle for 2021-12 is a little bit different than the classical one. M1 is one week shorter than usual in order to release 2021-12 not too close to the Christmas period. I updated the schedule last week. Please have in mind the new dates:

2021-12 M1	Friday, October 08, 2021	10/01 to 10/08	
Opt-in deadline (new projects only)
Create your release record (for new releases)
CQ Submission deadline (new third-party content)
2 weeks from 2021-09 GA

2021-12 M2	Friday, October 29, 2021	10/22 to 10/29		3 weeks from M1

2021-12 M3	Friday, November 19, 2021	11/12 to 11/19	
IP Log submission deadline
3 weeks from M2

2021-12 RC1	Friday, November 26, 2021	11/19 to 11/26	
No new features and APIs after this date!
Release Review materials due
New and Noteworthy entries due
1 week from M3

2021-12 RC2	Friday, December 3, 2021	11/26 to 12/03		1 week from RC1

Quiet period 12/03 to 12/07 No builds during "quiet period". It is assumed all code is done by the end of RC2.

2021-12 GA	Wednesday, December 08, 2021		
Release reviews conclude on this date
5 days from RC2

See all the details on the wiki:
https://wiki.eclipse.org/Category:SimRel-2021-12

Best regards,
--
Mélanie Bats
CTO
+33 7 87 69 42 84
@melaniebats

*Obeo*
25 Boulevard Victor Hugo - Colomiers - France
http://www.obeo.fr


Back to the top