[cross-project-issues-dev] 2021-12 Schedule changed
|
Hi,
Pay attention that the release cycle for 2021-12 is a little bit
different than the classical one. M1 is one week shorter than usual in
order to release 2021-12 not too close to the Christmas period. I
updated the schedule last week. Please have in mind the new dates:
2021-12 M1 Friday, October 08, 2021 10/01 to 10/08
Opt-in deadline (new projects only)
Create your release record (for new releases)
CQ Submission deadline (new third-party content)
2 weeks from 2021-09 GA
2021-12 M2 Friday, October 29, 2021 10/22 to 10/29 3 weeks from M1
2021-12 M3 Friday, November 19, 2021 11/12 to 11/19
IP Log submission deadline
3 weeks from M2
2021-12 RC1 Friday, November 26, 2021 11/19 to 11/26
No new features and APIs after this date!
Release Review materials due
New and Noteworthy entries due
1 week from M3
2021-12 RC2 Friday, December 3, 2021 11/26 to 12/03 1 week from RC1
Quiet period 12/03 to 12/07 No builds during "quiet period". It is
assumed all code is done by the end of RC2.
2021-12 GA Wednesday, December 08, 2021
Release reviews conclude on this date
5 days from RC2
See all the details on the wiki:
https://wiki.eclipse.org/Category:SimRel-2021-12
Best regards,
--
Mélanie Bats
CTO
+33 7 87 69 42 84
@melaniebats
*Obeo*
25 Boulevard Victor Hugo - Colomiers - France
http://www.obeo.fr