Re: [cross-project-issues-dev] SimRel 2019-06 Release Candidate 2 (RC2) staging repo is complete

I can live without it :-)

I agree with Doug though, it should probably be better documented when the last contribution can be made. Since the iterations come so frequently now, it’s hard to keep up with where we are in a cycle.

Regards,
Greg

On Jun 13, 2019, at 12:10 PM, Doug Schaefer <dschaefer@xxxxxxxxxxxxxx> wrote:

If that's the rule, it should really be captured here:

https://wiki.eclipse.org/SimRel/2019-06/Simultaneous_Release_Plan

Also interesting that the GA date keeps getting earlier. We're in mid-June territory now...

Doug.

________________________________________
From: cross-project-issues-dev-bounces@xxxxxxxxxxx [cross-project-issues-dev-bounces@xxxxxxxxxxx] on behalf of Frederic Gurr [frederic.gurr@xxxxxxxxxxxxxxxxxxxxxx]
Sent: Thursday, June 13, 2019 12:04 PM
To: cross-project-issues-dev@xxxxxxxxxxx
Subject: Re: [cross-project-issues-dev] SimRel 2019-06 Release Candidate 2 (RC2) staging repo is complete

Hi,

The quiet period officially starts tomorrow, but the EPP build is always
on a Thursday. Unfortunately, last minute contributions have started to
bleed into Thursday for a while now, even though they should be done by
Wednesday EOB.

Are you okay with leaving out that change?

Regards,

Fred

On 13.06.19 17:58, Greg Watson wrote:
No, not critical, but I thought tomorrow was the start of the RC2 quiet period?

Greg

On Jun 13, 2019, at 11:45 AM, Frederic Gurr <frederic.gurr@xxxxxxxxxxxxxxxxxxxxxx> wrote:

Hi,

Is this a critical fix?

Regards,

Fred

On 13.06.19 16:24, Greg Watson wrote:
I have an update that only went into the build today because a previous Gerrit changeset was never validated. Is it possible to run the aggregation again today? Sorry for the last minute issue.

Thanks,
Greg

On Jun 13, 2019, at 9:43 AM, Frederic Gurr <frederic.gurr@xxxxxxxxxxxxxxxxxxxxxx> wrote:

Hi,

Since the SimRel aggregator build is quiet, I declare the staging repo
for 2019-06 RC2 to be complete.

As usual, it can be found here:

=> https://urldefense.proofpoint.com/v2/url?u=http-3A__download.eclipse.org_staging_2019-2D06_&d=DwICAg&c=yzoHOc_ZK-sxl-kfGNSEvlJYanssXN3q-lhj0sp26wE&r=NrrbvTHWa2Nbp_kAN0Hl1o3lM1WAwSes64uBjxjNhMc&m=Kxo5hO9B2vR-RsF79RhPB4XXe9-ohDFoJvX3O40qggU&s=yyVFt7Kg-duKjZ89Yo9TCo-e3CcfHTVh4J9mMbNFX0M&e=

Please note, we will enter quiet days for 2019-06. If no blocking
issues are found, RC2 will become the official 2019-06 release on
Wednesday, June 19th.

Thanks for all your contributions and happy _quiet_ days!

Regards,

Fred



--
Frederic Gurr
Release Engineer | Eclipse Foundation Europe GmbH

Annastr. 46, D-64673 Zwingenberg
Handelsregister: Darmstadt HRB 92821
Managing Directors: Ralph Mueller, Mike Milinkovich, Chris Laroque
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://urldefense.proofpoint.com/v2/url?u=https-3A__www.eclipse.org_mailman_listinfo_cross-2Dproject-2Dissues-2Ddev&d=DwICAg&c=yzoHOc_ZK-sxl-kfGNSEvlJYanssXN3q-lhj0sp26wE&r=NrrbvTHWa2Nbp_kAN0Hl1o3lM1WAwSes64uBjxjNhMc&m=Kxo5hO9B2vR-RsF79RhPB4XXe9-ohDFoJvX3O40qggU&s=Ys6M874QOeeDzWafEyaZs0kC6STit_ELSN-vnRBUS1g&e=

_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://urldefense.proofpoint.com/v2/url?u=https-3A__www.eclipse.org_mailman_listinfo_cross-2Dproject-2Dissues-2Ddev&d=DwICAg&c=yzoHOc_ZK-sxl-kfGNSEvlJYanssXN3q-lhj0sp26wE&r=NrrbvTHWa2Nbp_kAN0Hl1o3lM1WAwSes64uBjxjNhMc&m=Kxo5hO9B2vR-RsF79RhPB4XXe9-ohDFoJvX3O40qggU&s=Ys6M874QOeeDzWafEyaZs0kC6STit_ELSN-vnRBUS1g&e=


--
Frederic Gurr
Release Engineer | Eclipse Foundation Europe GmbH

Annastr. 46, D-64673 Zwingenberg
Handelsregister: Darmstadt HRB 92821
Managing Directors: Ralph Mueller, Mike Milinkovich, Chris Laroque
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://urldefense.proofpoint.com/v2/url?u=https-3A__www.eclipse.org_mailman_listinfo_cross-2Dproject-2Dissues-2Ddev&d=DwICAg&c=yzoHOc_ZK-sxl-kfGNSEvlJYanssXN3q-lhj0sp26wE&r=NrrbvTHWa2Nbp_kAN0Hl1o3lM1WAwSes64uBjxjNhMc&m=Kxo5hO9B2vR-RsF79RhPB4XXe9-ohDFoJvX3O40qggU&s=Ys6M874QOeeDzWafEyaZs0kC6STit_ELSN-vnRBUS1g&e=
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://www.eclipse.org/mailman/listinfo/cross-project-issues-dev


Back to the top