[cross-project-issues-dev] Reminder we start "1 week window" for M4
|
Since I had to clear this up in TWO meetings I was at today ... I figured I
would remind everyone else, too.
The platform M4 (+0 day) is scheduled for Friday, 12/9.
The Simultaneous M4 is scheduled for 12/16. One week later!
See
http://wiki.eclipse.org/Juno/Simultaneous_Release_Plan#Schedule
This means Monday (12/12) is +1, Tuesday (12/13) is +2 and Wednesday
(12/14) is +3 with EPP builds and tests on Thursday, 12/15. The final
"aggregation build" will be expected to be 12/14 roughly 5 PM Eastern. All
declared and made visible the morning of 12/16.
We do this "shrinkage" to 1 week in December primarily due to the holidays
(12/23 doesn't sound like a safe deadline for anything)
but we always want to get to "1 week" at some point, so we've always done
it in December.
I was going to send this reminder next week ... but ... since the two
groups I was talking to today should have known better :) I thought an
earlier reminder would be best.
I suspect it won't be an "easy" milestone ... given some version changes,
(one obvious one is "javax.servlet" ... I know it effects WTP:
http://dev.eclipse.org/mhonarc/lists/wtp-dev/msg08294.html)
so I appreciate everyone's (calm and patient :) progress towards this
final milestone for 2011.
Let us know if issues or questions.
Much thanks,