Hello Anne,
I have some questions related to Memory
Analyzer.
First some background: We had recently our
graduation / move/ release 1.0 review. We are just doing the post-move changes (legal,
webmaster and emo finished their work), and we still haven’t published
for download a 1.0 release. Our initial thinking was to have a 1.0 added to M7
and if bugfixes are needed – add a 1.0.1 to the final Helios release. We
somehow didn’t manage to finish everything on time for M7 and I’m
planning now like this:
- we add another milestone build to M7
(still not our 1.0 which was reviewed)
- we spend some further time on testing
and publish 1.0 downloadable about 14 May (one week before RC1)
- add MAT 1.0 to RC1
- take part in the review on 28 May, but
don’t make another release (e.g. 1.0.1)
Finally the questions:
-
if we
follow this plan, do we need to submit IP log again?
-
Do we
need another set of slides for the review on 28 May?
-
Can we
really put our 1.0 in RC1 and stick to it for Helios, or is it obligatory to
have another release made on 28 May
One more remark – I just copied all
the data from the simultaneous release tracker of technology.mat to tools.mat, the
technology.mat is still visible on the list here: http://eclipse.org/helios/planning/SimultaneousReleaseGrid.php?showallprojects=true
. What should I do to remove it from this list?
Sorry for asking too often, but I still
need to learn and build my experience as project lead at Eclipse.
Regards,
Krum
From: cross-project-issues-dev-bounces@xxxxxxxxxxx
[mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] On Behalf Of Anne Jacko
Sent: Donnerstag, 6. Mai 2010
07:50
To:
cross-project-issues-dev@xxxxxxxxxxx
Cc: emo-ip-team@xxxxxxxxxxx
Subject: [cross-project-issues-dev]
Helios review -- important dates
Hello Helios participants,
Thanks for your continuing work on making the
upcoming release train a success! Here's some information about getting ready
for the review. Unlike most reviews, we'll do this one on a conference call.
The conference call numbers are listed in the Portal [1].
Important dates:
IP Logs due: Friday, May 28
Docuware due: Friday, May 28
Helios Review: Friday, June 11
Helios Release: Wednesday, June 23
IP Log: Please use the IP Log tool to submit your
IP Log. If it doesn't work for your project for some reason, please submit your log manually to emo-ip-team@xxxxxxxxxxx.
Docuware: In addition to the regular review
docuware, please submit a very simple, brief additional file that summarizes
what you are bringing to the release -- just one or two paragraphs, or a few
bullet points is all we're looking for here. We'll combine the short files
to create a longer one that applies to the entire release.
Please note that simple text files
are fine for reviews -- there is no requirement to create a presentation-style
document. As long as the required information is there, you can use whatever
format you prefer. A list of required docuware contents is on the Eclipse wiki.
[2]