From:
cosmos-dev-bounces@xxxxxxxxxxx [mailto:cosmos-dev-bounces@xxxxxxxxxxx] On Behalf Of Ebright, Don
Sent: Tuesday, October 09, 2007
12:33 PM
To: Cosmos Dev
Subject: RE: [cosmos-dev] Vote
Requested: Revised Schedule for COSMOS 1.0
+1
I would actually prefer to have
preliminary designs in hand prior to the start of an iteration rather than
partition the interval into a design phase and a coding phase.
The contents of this e-mail are intended for the named addressee only.
It contains information that may be confidential. Unless you are the named
addressee or an authorized designee, you may not copy or use it, or disclose it
to anyone else. If you received it in error please notify us immediately and
then destroy it.
From:
cosmos-dev-bounces@xxxxxxxxxxx [mailto:cosmos-dev-bounces@xxxxxxxxxxx] On Behalf Of Mark D Weitzel
Sent: Tuesday, October 09, 2007
11:32 AM
To: Cosmos Dev
Cc: Cosmos Dev; cosmos-dev-bounces@xxxxxxxxxxx
Subject: Re: [cosmos-dev] Vote
Requested: Revised Schedule for COSMOS 1.0
+1
agree with ali's comment
_______________________________________________________________________________________________________________
Mark Weitzel | STSM | IBM Software Group | Tivoli | Autonomic Computing | (919) 543 0625
| weitzelm@xxxxxxxxxx
![]()
|
Re: [cosmos-dev] Vote
Requested: Revised Schedule for COSMOS 1.0
|
Ali Mehregani
|
to:
|
Cosmos Dev
|
10/09/07
10:49 AM
|
Sent by:
|
cosmos-dev-bounces@xxxxxxxxxxx
|
Please respond to Cosmos Dev
<cosmos-dev@xxxxxxxxxxx>
|
|
|
+1
My only comment is to have the development block broken down into a design and
implementation phase.
Thanks,
Ali Mehregani
On 10/4/07, Tania N Makins <tmakins@xxxxxxxxxx> wrote:
COSMOS Committers,
I have updated the proposal for schedule revisions, per our discussion during
today's Community Call: http://wiki.eclipse.org/Cosmos_Release_Plan#Proposed_Revisions_i7-i12_.2810.2F04.2F2007.29_-_Release_Milestones.
Summary of changes:
- Moved Milestone 2 to the
end of i9, which is March 7. This milestone will be used for
EclipseCon 2008.
- Removed Milestone 3, which
was originally scheduled for the end of i10.
Please review the latest proposal and post your vote by end of day tomorrow,
October 5.
Tania N. Makins
Project Manager, AC Open Source Components
IBM Software Group - RTP,
NC
Office: (919) 254-8430 T/L: 444-8430
tmakins@xxxxxxxxxx
_______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev
--
Ali Mehregani
Test & Performance Tools Platform
http://www.eclipse.org/tptp _______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev