what is the final schedule?  Is it as detailed on the wiki?  Or are there more
updates planned?
 
Jimmy Mohsin
VP, Principal Architect
Office of the CTO
Cell   +1-609-635-1703
 
From:
cosmos-dev-bounces@xxxxxxxxxxx [mailto:cosmos-dev-bounces@xxxxxxxxxxx] On
Behalf Of Mark D Weitzel
Sent: Tuesday, October 02, 2007 1:06 PM
To: Mohsin, Jimmy
Cc: Cosmos Dev
Subject: RE: [cosmos-dev] Vote Requested: Revised Schedule for COSMOS
1.0
 
 
Tania, 
The thinking is
that we want to close i8 on 28-Dec.  We realize given the holidays that
the content will likely be much less that we might normally target. 
We'll need to
coordinate with Balan to ensure we can get the candidate builds out.
 We'll also need to figure out test coverage of i8 given vacation
schedules. 
-mw   
_______________________________________________________________________________________________________________
Mark Weitzel | STSM | IBM Software Group | Tivoli | Autonomic Computing | (919)
543 0625 | weitzelm@xxxxxxxxxx 
 
  | 
   ![]()  
   | 
  
  
   
    | 
     RE:
    [cosmos-dev] Vote Requested: Revised Schedule for COSMOS 1.0 
     | 
    
   
    
  
   
    | 
     Mohsin, Jimmy  
     | 
    
     to:  
     | 
    
     Cosmos
    Dev  
     | 
    
     10/02/07 11:47 AM 
     | 
    
   
    
  
   | 
 
 
 
  
Tania, 
  
We talked about this
on the DC call today… Can we close off i8 BEFORE the (calendar) year ends?
 Please follow up with Mark if you need further details, as there are
vacation considerations here. 
  
Thanks, 
Jimmy Mohsin 
+1-609-635-1703
From:
cosmos-dev-bounces@xxxxxxxxxxx [mailto:cosmos-dev-bounces@xxxxxxxxxxx] On
Behalf Of Tania N Makins
Sent: Tuesday, October 02, 2007 10:44 AM
To: cosmos-dev@xxxxxxxxxxx
Subject: [cosmos-dev] Vote Requested: Revised Schedule for COSMOS 1.0
  
COSMOS Committers, 
Please post your vote for the revised COSMOS 1.0 Release Schedule: http://wiki.eclipse.org/Cosmos_Release_Plan#Proposed_Revisions_i7-i12_.289.2F28.2F2007.29_-_Release_Milestones.
Tania 
   Tania N. Makins
   Project Manager, AC Open Source Components
   IBM Software Group - RTP, NC
   Office: (919) 254-8430  T/L: 444-8430
   tmakins@xxxxxxxxxx 
----- Forwarded by Tania N Makins/Durham/IBM on 10/02/2007 10:40 AM -----
 
  | 
   Tania
  N Makins/Durham/IBM@IBMUS  
  Sent by: cosmos-dev-bounces@xxxxxxxxxxx  
  10/01/2007
  03:59 PM  
    
  
   
    | 
     Please respond to 
    Cosmos Dev <cosmos-dev@xxxxxxxxxxx> 
     | 
    
   
   | 
  
     
  
   
    | 
     To 
     | 
    
     cosmos-dev@xxxxxxxxxxx
     
     | 
    
   
    | 
     cc 
     | 
     | 
    
   
    | 
     Subject 
     | 
    
     [cosmos-dev]
    Reminder - Proposal: Revised Schedule for COSMOS 1.0 
     | 
    
   
   
     
    
  
   | 
 
So far, I have not seen any comments on the proposed schedule revisions.  Remember
to post questions or comments today, so I can make revisions and post for a
vote tomorrow. 
Tania 
  Tania N. Makins
  Project Manager, AC Open Source Components
  IBM Software Group - RTP, NC
  Office: (919) 254-8430  T/L: 444-8430
  tmakins@xxxxxxxxxx 
----- Forwarded by Tania N Makins/Durham/IBM on 10/01/2007 03:56 PM -----
 
  | 
   Tania
  N Makins/Durham/IBM@IBMUS  
  Sent by: cosmos-dev-bounces@xxxxxxxxxxx  
  09/28/2007
  06:42 PM  
    
  
   
    | 
     Please respond to 
    Cosmos Dev <cosmos-dev@xxxxxxxxxxx> 
     | 
    
   
   | 
  
     
  
   
    | 
     To 
     | 
    
     cosmos-dev@xxxxxxxxxxx
     
     | 
    
   
    | 
     cc 
     | 
     | 
    
   
    | 
     Subject 
     | 
    
     [cosmos-dev]
    Proposal: Revised Schedule for COSMOS 1.0 
     | 
    
   
   
     
    
  
   | 
 
Team, 
I have posted a proposal for a revised Milestone plan for COSMOS 1.0 on the
wiki, just below the current plan: http://wiki.eclipse.org/Cosmos_Release_Plan#Proposed_Revisions_i7-i12_.289.2F28.2F2007.29_-_Release_Milestones.
The key changes to note in this proposal are: 
- The start of i7 moves to Oct. 3 
- Milestone 2 moves to Jan. 25 (the end of i8) 
- Milestone 3 moves to Apr. 25 (the end of i10) 
An alternative would be to: 
- Set Milestone 2 for Nov. 28 (make the test pass for i7 2 weeks) 
- Set Milestone 3 for March 7, just before EclipseCon (shorten the development
cycle for i9 to 4 weeks, make the test pass 2 weeks) 
Please post your comments by end of day Monday.  I will incorporate
feedback into the schedule, and post the revised schedule for a vote on Tuesday
morning. 
 Tania N. Makins
 Project Manager, AC Open Source Components
 IBM Software Group - RTP, NC
 Office: (919) 254-8430  T/L: 444-8430
 tmakins@xxxxxxxxxx_______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev_______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev