Re: Connection between Lane and Activity [message #616653 is a reply to message #616650] |
Wed, 28 May 2008 15:24 |
Eclipse User |
|
|
|
Originally posted by: atoulme.intalio.com
Hi Till, it is a work in progress.
We know how to do it, since we did it for groups, but did not have time
to implement it.
See https://bugs.eclipse.org/bugs/show_bug.cgi?id=233472
Thanks,
Antoine
Till Essers wrote:
> Hi
>
> I had a look into the diagram file and found, that there is no
> connection between the Lanes and its Activities.
> The problem is, I wanted to add users to the Lane in order to get a
> better overview for the designer of the workflow and add the users from
> the Lane to our internal activities which will be deployed into our
> workflow system.
> Is there no connection between Lane and Activity or is it me doing
> anything wrong?
> Is it not yet implemented?
>
> Thanks
> Till
|
|
|
|
Re: Connection between Lane and Activity [message #616678 is a reply to message #616675] |
Sat, 14 June 2008 06:00 |
Eclipse User |
|
|
|
Originally posted by: atoulme.intalio.com
It is now implemented and part of the 1.0 release gearing up for ganymede.
Thanks,
Antoine
Maria Agustina Cibran wrote:
> could you give an estimated time for the implementation of a solution to
> this problem? This is crucial for the adoption of the stp bpmn metamodel
> in the implementation of model transformations...
>