Gannt Chart - Date from and Date to [message #478719] |
Thu, 06 August 2009 14:20 |
|
Hello,
is it possible to set the start date and end date in the GanntChart?
For example I have data from 01.09.2009 until 14.09.2009 and would like to
set the initial displayed data in timeline of the Gannt Chart. The default
is that 9 months are displayed.
Best regards, Lars
|
|
|
Re: Gannt Chart - Date from and Date to [message #479153 is a reply to message #478719] |
Sun, 09 August 2009 21:15 |
|
Solved by chart.getGanttComposite().setZoomLevel(3); which does what I
want. Thanks.
Lars Vogel wrote:
> Hello,
>
> is it possible to set the start date and end date in the GanntChart?
>
> For example I have data from 01.09.2009 until 14.09.2009 and would like
> to set the initial displayed data in timeline of the Gannt Chart. The
> default is that 9 months are displayed.
>
> Best regards, Lars
>
--
http://www.vogella.de/ - Eclipse plugin and Eclipse RCP Tutorials
http://www.twitter.com/vogella - vogella on Twitter
|
|
|
Re: Gannt Chart - Date from and Date to [message #598090 is a reply to message #478719] |
Sun, 09 August 2009 21:19 |
|
Solved by chart.getGanttComposite().setZoomLevel(3); which does what I
want. Thanks.
Lars Vogel wrote:
> Hello,
>
> is it possible to set the start date and end date in the GanntChart?
>
> For example I have data from 01.09.2009 until 14.09.2009 and would like
> to set the initial displayed data in timeline of the Gannt Chart. The
> default is that 9 months are displayed.
>
> Best regards, Lars
>
--
http://www.vogella.de/ - Eclipse plugin and Eclipse RCP Tutorials
http://www.twitter.com/vogella - vogella on Twitter
|
|
|
Powered by
FUDForum. Page generated in 0.02798 seconds