| RSE 1.0 new dates (release moved by 2 weeks) [message #1587] | Wed, 18 October 2006 12:08 |  | 
| Eclipse User  |  |  |  |  | Dear all, 
 We just discussed in the Target Management committer meeting that we'll
 have 2 more release candidates of RSE 1.0 in order to address some
 hi-priority bugs discovered during the coordinated test phase. This is
 in line with the project plan, which had planned for a series of
 test-fix passes until a "go" is achieved from all committers.
 
 We'll also have 1 more round of testing (1 day only) so here's the
 new Endgame plan. Also note that the TM Open Phone Call is now scheduled
 for November 8th, just right to celebrate our release:
 
 Friday Oct. 20   -- RSE 1.0 RC2
 Friday Oct. 27   -- RSE 1.0 RC3
 Monday Oct. 30 -- RSE Testing round 3 (single day only)
 Focus will be on verification of hi-severity fixes,
 and sanity testing typical user actions
 Friday Nov. 3    -- RSE 1.0 RELEASE
 Wednesday Nov. 8 -- TM Open Phone Call
 
 I'd appreciate if lots of you could download and check the release
 candidates, send bug reports, and also sign up for the 3rd round of testing.
 
 For any bug reports you want to make, if you already have a bug
 entry template from test rounds 1 or 2, please use it since the
 extra information about your system configuration is really helpful
 for us.
 
 Thanks,
 Martin
 
 --
 Martin Oberhuber
 Wind River Systems, Inc.
 Target Management Project Lead, DSDP PMC Member
 http://www.eclipse.org/dsdp/tm
 |  |  |  | 