| Can artefact versions be modelled using EPF? [message #49396] | Wed, 16 April 2008 09:42 |  | 
| Eclipse User  |  |  |  |  | Originally posted by: padraig.oleary.lero.ie 
 Hey Everyone,
 
 I have a question regarding the handling of artefacts within EPF. I am
 modelling a product derivation process within a SPL organisation. I have a
 number of tasks
 
 I have multiple tasks within a specific requirements handling phase. Each
 task takes the output of the previous task as input. The artefact in
 question (a requirements document), is essentially passed along within the
 phase with each task making some change to the artefact. I am currently
 handling the different 'versions' of this single artefact by creating
 multiple copies and naming them XXXver0.1, XXXver0.2 etc, which each
 artefact 'version' describing the change it has undergone.
 
 Is there a better way of handling this? Is it a limitation of EPF or am I
 taking the wrong approach?
 
 Any advice, potential solutions, etc. greatly appreciateed,
 
 Regards,
 Pádraig
 |  |  |  | 