STEM Migration Plans and Release Schedule [message #3359] |
Wed, 10 June 2009 14:15 |
Eclipse User |
|
|
|
STEM Migration Plans and Release Schedule
Decisions reached during the regularly scheduled weekly STEM developers
call
June 3, 2009
On call: Jamie, Matt, Stefan, Werner, Judy
MIGRATION PLAN
Decision: Freeze code and refactor June 3, 2009, using the new version
Do stepwise. Refactor first (delete projects now defunct), then move
Vote: Unanimous, no objections
Decision: Determine how other Eclipse projects organizing directories,
renaming, etc.
Matt will investigate
Vote: Unanimous, no objections
Decision: Complete source code migration June 30, 2009
Matt will check Eclipse rules for moving from incubation status
Vote: Unanimous, no objections
RELEASE SCHEDULE
Decision: First release of STEM with current features September 15, 2009
Will review all bugs to determine which need to be fixed; also review
technical and legal issues
Vote: Unanimous, no objections
Decision: Follow-on release with multiple population functionalities
November 30, 2009
Stefan will check with Dan to get his list for incorporation into the
release plan
Vote: Unanimous, no objections
Item: Next big milestone OSGi
Item: Change version numbering, starting w/ 10.0, feature build 2.0.0, etc.
Item: Check w/ Yossi re weekly update
|
|
|