Re: Specifying work products that appear in Work Product Breakdown [message #1693274 is a reply to message #1648220] |
Wed, 22 April 2015 15:40  |
Eclipse User |
|
|
|
The behavior is not as described.
It's not all work products in the database that appear under the phase, but rather all work products used as input or output by any task anywhere in the phase.
I find that is a lot of noise, so I choose skins that don't display that information.
What tends to be more interesting to me is the "goal" or "interface" work products of a phase. I.e. It would be nice if the tool could be used to specify which work products come in at the start of a phase and are outputs of the phase.
On a milestone element (which can be placed at the end of a phase) you can specify the required results of the milestone. You may find that helpful.
If using RMC, you could use user-defined types to add a new relationships to a phase such as Phase inputs / Phase outputs.
Hope that helps,
Bruce
|
|
|