TPTP 4.7.2 Detailed Schedule

Duration: 18 weeks

References:

        Helios SR2 Plan

 

 

 

Task Name

Duration

Start Date

Finish Date

Notes

4.7.2

18 weeks

Mon 09/27/2010

Wed 02/16/2011

Defect Fixing.

 

 

 

 

 

 

 

 

 

 

4.7.2 Iteration 1

 

 

 

 

4.7.2 I1 Development

5 weeks

Mon 09/27/2010

Fri 10/30/2010

 

4.7.2 I1 Smoke test

2 days

Thurs 11/04/2010

Fri 11/05/2010

Project approval mode

 

 

 

 

 

4.7.2 Iteration 2

 

 

 

 

4.7.2 I2 Development

6 weeks

Mon 11/08/2010

Wed 12/08/2010

 

4.7.2 I2 Smoke test

2 days

Thur 12/09/2010

Tues 12/10/2010

Project Approval Mode

4.7.2 I2 TP1

1 weeks

Mon 12/13/2010

Fri 12/17/2010

Project Approval Mode

 

 

 

 

 

Fix any blocking issues from 4.7.2 I2 TP1

1 week

Mon 12/20/2010

Fri 01/07/2010

Project Approval Mode

Drop to Helios SR2 (RC1)

 

Tue 01/18/2011

Wed 01/19/2011

 

Fix critical defects

1 week

Mon 01/10/2011

Fri 01/21/2011

Project Approval Mode

Drop to Helios SR2 (RC2)

 

Tue 02/01/2011

Wed 02/02/2011

 

 

 

 

 

 

4.7.2 I2 regression testing

3 week

Mon 01/24/2011

Fri 02/11/2011

PMC Approval Mode

Drop to Helios SR2 (RC3)

 

Tue 02/08/2011

Wed 02/09/2011

 

Drop to Helios SR2 (RC4)

 

Tue 02/15/2011

Wed 02/16/2011

 

Helios SR2 General Availability

 

Fri 02/25/2011

Fri 02/25/2011