TPTP 4.7.1 Detailed Schedule

Duration: 12 weeks

References:

        Helios SR1 Plan

 

 

Task Name

Duration

Start Date

Finish Date

Notes

4.7.1

12 weeks

Thu 06/24/2010

Wed 09/15/2010

Defect Fixing.

4.7.1 Development

8 weeks

Thu 06/24/2010

Wed 08/20/2010

 

4.7.1 Smoke testing

2 days

Thu 08/05/2010

Fri 08/06/2010

Project Approval Mode

Drop to Helios SR1 (RC1)

 

Tue 08/10/2010

Wed 08/11/2010

 

4.7.1 TP

1 weeks

Mon 08/23/2010

Fri 08/27/2010

Project Approval Mode

Drop to Helios SR1 (RC2)

---

Tue 08/31/2010

Wed 09/01/2010

 

Fix any blocking issues from 4.7.1 TP

2 week

Mon 08/30/2010

Fri 09/10/2010

PMC Approval Mode

Drop to Helios SR1 (RC3)

 

Tue 09/07/2010

Wed 09/08/2010

 

Drop to Helios SR1 (RC4)

---

Tue 09/14/2010

Wed 09/15/2010

 

Helios SR1 General Availability

---

Fri 09/24/2010

Fri 09/24/2010