TPTP 4.6 Detailed Schedule

Duration: 18 weeks

References:

         Galileo Plan

 

 

 

Task Name

Duration

Start Date

Finish Date

Notes

1

4.6 Iteration 1

4.6 weeks

Mon 02/16/2009

Fri 03/13/2009

Defect Fixing.

2

4.6 I1 Development

3 weeks

Mon 02/16/2009

Fri 03/06/2009

 API/UI Freeze

3

4.6 I1 Test Pass

1 week

Mon 03/09/2009

Fri 03/13/2009

Project Approval Mode.

2

Drop to Galileo M6 +2

3 days

Mon 03/16/2009

Wed 03/18/2009

 

4

4.6 Iteration 2

7.4 weeks

Mon 3/16/2009

Fri 05/01/2009

Defect Fixing.

5

4.6 I2 Development

5 weeks

Mon 03/16/2009

Fri 04/17/2009

Feature Freeze

6

4.6 I2 Test Pass

2 weeks

Mon 04/20/2009

Fri 05/01/2009

Project Approval Mode.

2

Drop to Galileo M7 +2

2 days

Mon 05/04/2009

Tue 05/05/2009

 

7

4.6 Iteration 3

6 weeks

Mon 05/04/2009

Fri 06/12/2009

Defect Fixing.

8

4.6 I3 Development

1 week

Mon 05/04/2009

Fri 05/08/2009

 

9

4.6 I3 shutdown

1 week

Mon 05/11/2009

Fri 05/15/2009

Project Approval Mode.

10

4.6 I3 TP1

2 weeks

Mon 05/18/2009

Wed 06/03/2009

 PMC Approval Mode.

11

Drop TPTP 4.6 I3 TP1 driver to Galileo RC1

---

Tue 05/19/2009

Tue 05/19/2009

 

12

Drop TPTP 4.6 I3 TP1 driver to Galileo RC2

---

Tue 05/26/2009

Tue 05/26/2009

 

14

Drop TPTP 4.6 I3 TP1 driver to Galileo RC3

---

Tue 06/02/2009

Tue 06/02/2009

 

13

4.6 I3 TP2

1 week

Thu 06/04/2009

Fri 06/12/2009

 PMC Approval Mode.

15

Drop TPTP 4.6 I3 TP2 driver to Galileo RC4

---

Tue 06/09/2009

Tue 06/09/2009

 

17

Drop TPTP 4.6 I3 TP2 driver to Galileo RC5

---

Tue 06/16/2009

Tue 06/16/2009

 

18

Galileo General Availability

---

Wed 06/24/2009

Wed 06/24/2009