TPTP 4.6.2 Detailed Schedule

Duration: 18 weeks

References:

        Galileo SR2 Plan

        Helios Plan

 

 

 

Task Name

Duration

Start Date

Finish Date

Notes

4.6.2

18 weeks

Wed 09/23/2009

Tues 02/16/2010

Defect Fixing.

 

 

 

 

 

Drop to Helios M2

 

Mon 09/28/2009

Tues 09/29/2009

 

 

 

 

 

 

4.6.2 Iteration 1

 

 

 

 

4.6.2 I1 Development

5 weeks

Mon 09/23/2009

Fri 10/30/2009

 

4.6.2 I1 Smoke test & TP1

1 week

Mon 11/02/2009

Fri 11/06/2009

Project approval mode

 

 

 

 

 

4.6.2 Iteration 2

 

 

 

 

4.6.2 I2 Development

6 weeks

Mon 11/09/2009

Fri 01/02/2010

Scheduled 2 weeks holidays

 

 

 

 

 

Smoke test on Helios

 

Wed 11/042009

Thu 11/05/2009

 

Drop to Helios M3

 

Mon 11/09/2009

Tues 11/10/2009

 

Test on Helios

1 week

Mon 11/30/2009

Fri 12/04/2009

 

Drop to Helios M4

 

Mon 12/14/2009

Tue 12/15/2009

 

 

 

 

 

 

4.6.2 I2 Smoke test/shutdown

1 week

Mon 01/04/2010

Fri 01/08/2010

Project Approval Mode

4.6.2 I2 TP1

2 weeks

Mon 01/11/2010

Fri 01/22/2010

Project Approval Mode

Drop to Galileo SR2 (RC1)

 

Tue 01/19/2010

Wed 01/20/2010

 

 

 

 

 

 

Drop to Galileo SR2 (RC2)

 

Tue 02/02/2010

Wed 02/03/2010

 

Fix any blocking issues from 4.6.2 I2 TP1

1 week

Mon 01/25/2010

Fri 01/29/2010

PMC Approval Mode

4.6.2 I2 regression testing

1 week

Mon 02/01/2010

Fri 02/05/2010

PMC Approval Mode

Drop to Galileo SR2 (RC3)

 

Tue 02/09/2010

Wed 02/10/2010

 

4.6.2 I2 regression testing

1 week

Mon 02/08/2010

Fri 02/12/2010

PMC Approval Mode

Drop to Galileo SR2 (RC4)

 

Tue 02/16/2010

Wed 02/17/2010

 

Galileo SR2 General Availability

 

Fri 02/26/2010

Fri 02/26/2010