TPTP 4.6.1 Detailed Schedule

Duration: 12 weeks

References:

        Galileo SR1 Plan

 

 

Task Name

Duration

Start Date

Finish Date

Notes

4.6.1

12 weeks

Wed 06/24/2009

Tues 09/15/2009

Defect Fixing.

4.6.1 Development

7 weeks

Wed 06/24/2009

Fri 08/07/2009

 

4.6.1 shutdown and smoke testing

1 week

Mon 08/10/2009

Fri 08/14/2009

Project Approval Mode

Drop to Galileo SR1 (RC1)

 

Tue 08/11/2009

Wed 08/12/2009

 

4.6.1 TP1

2 weeks

Mon 08/17/2009

Fri 08/28/2009

Project Approval Mode

Fix any blocking issues from 4.6.1 TP1

1 week

Mon 08/31/2009

Fri 09/04/2009

PMC Approval Mode

Drop to Galileo SR1 (RC2)

---

Tue 09/01/2009

Wed 09/02/2009

 

4.6.1 TP2

1 week

Tues 09/08/2009

Fri 09/11/2009

PMC Approval Mode

Drop to Galileo SR1 (RC3)

 

Tue 09/08/2009

Wed 09/09/2009

 

Drop to Galileo SR1 (RC4)

---

Tue 09/15/2009

Wed 09/16/2009

 

Galileo SR1 General Availability

---

Fri 09/25/2009

Fri 09/25/2009