TPTP 4.5 Detailed Schedule

Duration: 36 weeks

References:

         Ganymede Plan

         Weekly Schedule

 

 

 

Task Name

Duration

Start Date

Finish Date

Notes

1

4.5 Iteration 3

6 weeks

Wed 10/03/2007

Wed 11/14/2007

Defect Fixing + Unit Tests and Test Automation for API

2

4.5 I3 Development

3 weeks

Wed 10/03/2007

Wed 10/24/2007

 

3

4.5 I3 TP1

2 weeks

Wed 10/24/2007

Wed 11/07/2007

 

4

4.5 I3 TP2

1 week

Wed 11/07/2007

Wed 11/14/2007

 

5

Drop TPTP 4.5 I3 TP2 driver to Ganymede M3

---

Wed 11/14/2007

Wed 11/14/2007

 

6

4.5 Iteration 4

6 weeks

Thurs 11/15/2007

Fri 01/04/2008

Feature Development + additional defect fixing

7

4.5 I4 Development

3 weeks

Thurs 11/15/2007

Fri 12/07/2007

 

8

4.5 I4 TP1

1.5 weeks

Mon 12/10/2007

Wed 12/19/2007

 

9

Fix any blocking issues from 4.5 I4 TP1

0.5 weeks

Wed 12/19/2007

Fri 12/21/2007

 

10

4.5 I4 TP2

1 week

Mon 12/31/2007

Fri 01/04/2008

 

11

Drop TPTP 4.5 I4 TP2 driver to Ganymede M4

---

Fri 01/04/2008

Fri 01/04/2008

 

12

4.5 Iteration 5

6 weeks

Mon 01/07/2008

Fri 02/15/2008

Feature Development + additional defect fixing

13

4.5 I5 Development

3 weeks

Mon 01/07/2008

Fri 01/25/2008

 

14

4.5 I5 TP1

1.5 weeks

Mon 01/28/2008

Wed 02/06/2008

4.4.1 Test Pass

15

Fix any blocking issues from 4.5 I5 TP1

0.5 weeks

Wed 02/06/2008

Fri 02/08/2008

 

16

4.5 I5 TP1

1.5 week

Mon 02/04/2008

Wed 02/13/2008

 

17

Drop TPTP 4.5 I5 TP2 driver to Ganymede M5

---

Fri 02/15/2008

Fri 02/15/2008

 

18

4.5 Iteration 6

7 weeks

Mon 02/18/2008

Fri 04/04/2008

Additional defect fixing + API freeze

19

4.5 I6 Development

5 weeks

Mon 02/18/2008

Fri 03/21/2008

 

20

TPTP API Freeze

---

Fri 03/21/2008

Fri 03/21/2008

TPTP API Freeze

21

4.5 I6 TP1/Fix any blocking issues

1 week

Mon 03/24/2008

Fri 03/28/2008

 

22

4.5 I6 TP2

1 week

Mon 03/31/2008

Fri 04/04/2008

 

23

PII/Feature Freeze (I5 CVS stream)

---

Fri 04/04/2008

Fri 04/04/2008

 

24

Drop TPTP 4.5 I6 TP2 driver to Ganymede M6

---

Fri 04/04/2008

Fri 04/04/2008

 

25

4.5 Iteration 7

4 weeks

Mon 04/07/2008

Fri 05/02/2008

Critical and blocking defects

26

4.5 I7 Development

2 weeks

Mon 04/07/2008

Fri 04/18/2008

 

27

4.5 I7 TP1/Fix any blocking issues

1 week

Mon 04/21/2008

Fri 04/25/2008

 

28

4.5 I7 TP2

1 week

Mon 04/28/2008

Fri 05/02/2008

 

29

Drop TPTP 4.5 I7 TP2 driver to Ganymede M7

---

Fri 05/02/2008

Fri 05/02/2008

 

30

4.5 Iteration 8

5 weeks

Mon 05/05/2008

Fri 06/06/2008

Shutdown; Marching to 4.5 GA

31

4.5 I8 Development

1 week

Mon 05/05/2008

Fri 05/09/2008

Project Approval Mode

32

4.5 I8 TP1/Fix any blocking issues

2 weeks

Mon 05/12/2008

Fri 05/23/2008

PMC Approval Mode.

33

Drop TPTP 4.5 I8 TP1 driver to Ganymede RC1

---

Tue 05/20/2008

Tue 05/20/2008

 

34

Fix any blocking issues from 4.5 I8 TP1

1 week

Mon 05/26/2008

Fri 05/30/2008

PMC Approval Mode.

35

Drop TPTP 4.5 I8 TP1 driver to Ganymede RC2

---

Tue 05/27/2008

Tue 05/27/2008

 

36

4.5 I8 TP2

1 week

Mon 06/02/2008

Fri 06/06/2008

PMC Approval Mode.

37

Drop TPTP 4.5 I8 TP1 driver to Ganymede RC3

---

Tue 06/03/2008

Tue 06/03/2008

 

38

Drop TPTP 4.5 I8 TP2 driver to Ganymede RC4

---

Fri 06/06/2008

Fri 06/06/2008

 

39

Ganymede General Availability

---

Fri 06/25/2008

Fri 06/25/2008