TPTP 4.4.1 Detailed Schedule

Duration: 33 weeks


Task Name Duration Start Date Finish Date Notes
1 4.4.1 33 weeks Mon 07/16/2007 Mon 02/25/2008  
2 4.4.1 Development 22 weeks Mon 07/16/2007 Fri 01/25/2008  
3 4.4.1 Test Pass 2 weeks Mon 01/28/2008 Fri 02/08/2008 Full Test Pass
4 Fix any stop ship defects and regression test. 1 Week Mon 02/11/2008 Fri 02/15/2008 PMC Approved defects only. Test with latest Europa milestone
5 Regression Test with Europa Maintenance Release candidate 1 week Mon 02/18/2008 Fri 02/22/2008 Smoke Test
7 TPTP 4.4.1 Maintenance Release --- Mon 02/25/2008 Mon 02/25/2008 Update site refreshed with TPTP 4.4.1 driver
8 Europa Winter Maintenance Release --- Mon 02/25/2008 Mon 02/25/2008