Duration: 33 weeks
| Task Name | Duration | Start Date | Finish Date | Notes | |
|---|---|---|---|---|---|
| 1 | 4.4.1 | 33 weeks | Mon 07/16/2007 | Mon 02/25/2008 | |
| 2 | 4.4.1 Development | 22 weeks | Mon 07/16/2007 | Fri 01/25/2008 | |
| 3 | 4.4.1 Test Pass | 2 weeks | Mon 01/28/2008 | Fri 02/08/2008 | Full Test Pass |
| 4 | Fix any stop ship defects and regression test. | 1 Week | Mon 02/11/2008 | Fri 02/15/2008 | PMC Approved defects only. Test with latest Europa milestone |
| 5 | Regression Test with Europa Maintenance Release candidate | 1 week | Mon 02/18/2008 | Fri 02/22/2008 | Smoke Test |
| 7 | TPTP 4.4.1 Maintenance Release | --- | Mon 02/25/2008 | Mon 02/25/2008 | Update site refreshed with TPTP 4.4.1 driver |
| 8 | Europa Winter Maintenance Release | --- | Mon 02/25/2008 | Mon 02/25/2008 |