Duration: 11 weeks
| Task Name | Duration | Start Date | Finish Date | Notes | |
|---|---|---|---|---|---|
| 1 | 4.4.0.3 | 11 weeks | Mon 07/16/2007 | Fri 09/28/2007 | |
| 2 | 4.4.0.3 Development | 3 weeks | Mon 07/16/2007 | Fri 08/03/2007 | |
| 3 | 4.4.0.3 Test Pass | 1 week | Mon 08/06/2007 | Fri 08/10/2007 | Smoke Test Pass |
| 4 | Fix any stop ship defects and regression test. | 5 Weeks and 3 Days | Mon 08/13/2007 | Fri 09/19/2007 | PMC Approved defects only. Test with latest Europa milestone |
| 5 | Regression Test with latest Europa milestone driver | 1 week | Mon 09/20/2007 | Fri 09/26/2007 | Smoke Test |
| 6 | Regression Test with Europa Maintenance Release candidate | 2 Days | Mon 09/27/2007 | Fri 09/28/2007 | Smoke Test |
| 7 | TPTP 4.4.0.3 Maintenance Release | --- | Fri 09/28/2007 | Fri 09/28/2007 | Update site refreshed with TPTP 4.4.0.3 driver |
| 8 | Europa Fall Maintenance Release | --- | Fri 09/28/2007 | Fri 09/28/2007 |