TPTP 4.4.0.2 Detailed Schedule

Duration: 5 weeks


Task Name Duration Start Date Finish Date Notes
1 4.4.0.2 5 weeks Mon 07/16/2007 Fri 08/17/2007  
2 4.4.0.2 Development 3 weeks Mon 07/16/2007 Fri 08/03/2007 PMC Approved defects only
3 4.4.0.2 Test Pass 1 week Mon 08/06/2007 Fri 08/10/2007 Smoke Test Pass
4 Fix any stop ship defects and regression test. 1 Week Mon 08/13/2007 Fri 08/17/2007 PMC Approved defects only.
5 TPTP 4.4.0.2 Fix Pack Release --- Fri 08/17/2007 Fri 08/17/2007 Update site refreshed with TPTP 4.4.0.2 driver